QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.

Moor House Wind Farm

Moor House Wind Farm at Norton

Northern Powergrid Embedded Capacity Register 1MW and Over, November 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Date connected
14 Aug 2017
Status
Connected
Customer
Moor House Wind Farm
Site name
Moor House Wind Farm
Address
Moor House Wind Farm, Sadberge, Darlington, County Durham, DL2 1SN
Grid reference
Easting 433366, northing 518720
Licence area
North East (Northern Powergrid)
Grid supply point
Norton
Bulk supply point
Darlington North
Primary substation
Moor House Windfarm
Connection voltage
33 kV
Technology group
Wind
Energy source 1
Wind, Onshore wind turbines: 12.3 MW registered
Registered capacity
12.3 MW
Maximum export capacity
12.3 MW
Maximum import capacity
Not stated
Flexible connection
No
In a connection queue
Not published by Northern Powergrid
Date accepted
Not stated
Target energisation date
Not published by Northern Powergrid
Distribution reinforcement reference
Not published by Northern Powergrid
Transmission reinforcement reference
Not published by Northern Powergrid
Export MPAN
1574000328810
Import MPAN
Not stated
Last updated
8 Mar 2017
Tracked since
March 2026 edition

Change history

Tracked since the March 2026 edition, across 9 editions.

Changes to the details QueueWatch tracks, newest first.

No change to any detail QueueWatch tracks.

Also at Norton

GSP view

66 other sites at this grid supply point in the November 2026 edition. In all, the sites here total 2.0 GW: 0.4 GW connected, 1.6 GW accepted to connect.

See all 66

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?