EDF ENERGY RENEWABLES LIMITED
Customer named in the TEC register
Projects
Recent changes
- Hirfynydd and Mynydd DrumaurEngland and Wales, Storage with solar or windStage 1: Marked as Gate 1
- Hirfynydd and Mynydd DrumaurEngland and Wales, Storage with solar or windStage 2: Marked as Gate 1
- Correen Hills Wind FarmNorth Scotland, Onshore windMarked as Gate 1
- Watten Wind FarmNorth Scotland, Onshore windSubstation name updated in the register (from Mybster 3 GSP to Mybster 3 132/33kV Substation)
- Borders Wind FarmSouth Scotland, Onshore windMarked as Gate 1
- Dunside Wind Farm (Formally Fallago Rig 2 Wind Farm)South Scotland, Onshore windRenamed from Dunside Wind Farm
- Huntington Solar PVEngland and Wales, SolarMarked as Gate 1
- Cloich Forest Wind FarmSouth Scotland, Onshore windTransmission owner changed from SHET to SPT
- Kilbraur North Wind FarmNorth Scotland, Onshore windMarked as Gate 1
- Norwich 2England and Wales, Onshore windMarked as Gate 1
- Pollington HybridEngland and Wales, Storage with solar or windMarked as Gate 1
- Swansea NorthEngland and Wales, StorageMarked as Gate 1
- Penninghame Wind FarmSouth Scotland, Onshore windMarked as Gate 1
- Philiphaugh Wind FarmSouth Scotland, Onshore windMarked as Gate 1
- Swansea NorthEngland and Wales, StorageConnection date moved from 31 Oct 2026 to 31 Jul 2028 (+21 months)+21 mo
- Borders Wind FarmSouth Scotland, Onshore windTransmission owner changed from NGET to SPT
- Correen Hills Wind FarmNorth Scotland, Onshore windConnection point changed from Littlewoods Wind Farm 132/33kV Substation to Correen Hills Wind Farm 132kV Substation
- Garn Fach Wind FarmEngland and Wales, Storage with solar or windConnection point changed from Garn Fach 132kV Substation to MID WALES CONNECTION NODE A 400KV SUBSTATION
- Mynydd Y GwyntEngland and Wales, Storage with solar or windConnection point changed from Mynydd Y Gwynt 400kV Substation to MID WALES CONNECTION NODE A 400KV SUBSTATION
- Cloich Forest Wind FarmSouth Scotland, Onshore windConnection point changed from Cloiche 132kV Substation to Cloich 132kV Substation
- Correen Hills Wind FarmNorth Scotland, Onshore windRenamed from Littlewoods Wind Farm
- Dunside Wind Farm (Formally Fallago Rig 2 Wind Farm)South Scotland, Onshore windRenamed from Fallago Rig 2
- Sulgrave Solar PVEngland and Wales, SolarConnection point changed from East Claydon GSP (SEPD) to East Claydon GSP (NGED EM)
- Swansea NorthEngland and Wales, StorageCustomer changed from PIVOTED POWER LLP to EDF ENERGY RENEWABLES LIMITED
- Correen Hills Wind FarmNorth Scotland, Onshore windConnection date moved from 28 Sep 2029 to 30 Sep 2031 (+24 months)+24 mo
- Garn Fach Wind FarmEngland and Wales, Storage with solar or windCapacity changed from 110 MW to 162 MW
- Garn Fach Wind FarmEngland and Wales, Storage with solar or windConnection date moved from 1 May 2032 to 31 Oct 2037 (+66 months)+66 mo
- Garn Fach Wind FarmEngland and Wales, Storage with solar or windTechnology changed from Onshore wind to Storage, Onshore wind
- Heathland Wind FarmSouth Scotland, Storage with solar or windConnection date moved from 31 Mar 2027 to 29 Sep 2028 (+18 months)+18 mo
- Hirfynydd and Mynydd DrumaurEngland and Wales, Storage with solar or windRestructured from 1 stage (180 MW from 31 Oct 2029) to 2 stages (230 MW from 31 Oct 2030, 19.1 MW from 6 Dec 2036). First connection date +12 months+12 mo
- Huntington Solar PVEngland and Wales, SolarAdded to the registerNew
- Mynydd Y GwyntEngland and Wales, Storage with solar or windAdded to the registerNew
- Pollington HybridEngland and Wales, Storage with solar or windAdded to the registerNew
- Swansea NorthEngland and Wales, StorageStatus changed from Awaiting Consents to Scoping
- Correen Hills Wind FarmNorth Scotland, Onshore windConnection date moved from 31 Aug 2028 to 28 Sep 2029 (+13 months)+13 mo
- Hirfynydd and Mynydd DrumaurEngland and Wales, Storage with solar or windConnection date moved from 31 Oct 2028 to 31 Oct 2029 (+12 months)+12 mo
- Hirfynydd and Mynydd DrumaurEngland and Wales, Storage with solar or windTechnology changed from Solar, Onshore wind to Storage, Solar, Onshore wind
- Borders Wind FarmSouth Scotland, Onshore windTransmission owner changed from SPT to NGET
- Cloich Forest Wind FarmSouth Scotland, Onshore windConnection date moved from 30 Jul 2028 to 31 Jul 2029 (+12 months)+12 mo
- Cloich Forest Wind FarmSouth Scotland, Onshore windTransmission owner changed from SPT to SHET
- Norwich 2England and Wales, Onshore windTechnology changed from Storage, Solar to Solar, Onshore wind
- Philiphaugh Wind FarmSouth Scotland, Onshore windAdded to the registerNew
- Dunside Wind Farm (Formally Fallago Rig 2 Wind Farm)South Scotland, Onshore windConnection date moved from 30 Apr 2028 to 30 Apr 2029 (+12 months)+12 mo
- Sulgrave Solar PVEngland and Wales, SolarAgreement type changed from Direct Connection to Embedded
- Dunside Wind Farm (Formally Fallago Rig 2 Wind Farm)South Scotland, Onshore windConnection point changed from Fallago 400kV Substation to Fallago 400/33kV
- Heathland Wind FarmSouth Scotland, Storage with solar or windTechnology changed from Onshore wind to Storage, Onshore wind
- Watten Wind FarmNorth Scotland, Onshore windConnection point changed from Mybster 3 33kV Substation to Mybster 3 GSP
- Watten Wind FarmNorth Scotland, Onshore windConnection date moved from 30 Jun 2027 to 30 Jun 2028 (+12 months)+12 mo
- Watten Wind FarmNorth Scotland, Onshore windRenamed from Acharole Wind Farm
- Borders Wind FarmSouth Scotland, Onshore windTransmission owner changed from NGET to SPT
- Correen Hills Wind FarmNorth Scotland, Onshore windSubstation name updated in the register (from Littlewoods Wind Farm 132/33kV to Littlewoods Wind Farm 132/33kV Substation)
- Correen Hills Wind FarmNorth Scotland, Onshore windTransmission owner changed from NGET to SHET
- Norwich 2England and Wales, Onshore windTechnology changed from Solar, Onshore wind to Storage, Solar
- Borders Wind FarmSouth Scotland, Onshore windCapacity changed from 500 MW to 400 MW
- Borders Wind FarmSouth Scotland, Onshore windTransmission owner changed from SPT to NGET
- Correen Hills Wind FarmNorth Scotland, Onshore windTransmission owner changed from SHET to NGET
- Dunside Wind Farm (Formally Fallago Rig 2 Wind Farm)South Scotland, Onshore windConnection date moved from 30 Jan 2028 to 30 Apr 2028 (+3 months)+3 mo
- Dunside Wind Farm (Formally Fallago Rig 2 Wind Farm)South Scotland, Onshore windConnection date moved from 31 Jan 2028 to 30 Jan 2028 (1 day earlier)
- Borders Wind FarmSouth Scotland, Onshore windRenamed from Borders Wind Farms
- Dunside Wind Farm (Formally Fallago Rig 2 Wind Farm)South Scotland, Onshore windConnection date moved from 31 Oct 2023 to 31 Jan 2028 (+51 months)+51 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose