Swansea North 400kV Substation
England and Wales, National Grid Electricity Transmission
8projects in the register
2 GWstill to connect
0 MWof that with Gate 2 offers
21 MWconnected now
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Swansea Greener Grid Park - Connection 1 | SWANSEA GRID SOLUTIONS LIMITED | Storage | 97 | 31 Aug 2024 Past date | Not stated | Under construction |
| Swansea Greener Grid Park - Connection 2 | SWANSEA GRID SOLUTIONS LIMITED | Other | 0 | 31 Jul 2025 (0 MW) | Not stated | Consented |
| Swansea North | EDF ENERGY RENEWABLES LIMITED | Storage | 49.9 | 31 Jul 2028 | Gate 1 | Scoping |
| Swansea North Green Energy Centre | SWANSEA NORTH GREEN NG LIMITED | Storage with solar or wind | 1,025 | 30 Oct 2028 | Not stated | Scoping |
| BESS Swan | REWE 3 LIMITED | Storage | 200 | 31 Oct 2028 | Not stated | Scoping |
| Hirfynydd and Mynydd Drumaur | EDF ENERGY RENEWABLES LIMITED | Storage with solar or wind | 249 | 31 Oct 2030 | Gate 1 | Scoping |
| Swansea | ENSO GREEN HOLDINGS LIMITED | Storage with solar or wind | 400 | 31 Oct 2032 | Gate 1 | Scoping |
| Peak Gen Llandarcy | PEAK GEN POWER 5 LIMITED | Thermal (gas, biomass, waste) | 0 | Connected | Not stated | Built |
Recent changes
- Swansea North Green Energy CentreEngland and Wales, Storage with solar or windRestructured from 1 stage (1,025 MW from 31 Oct 2028) to 2 stages (400 MW from 30 Oct 2028, 625 MW from 31 Oct 2033)
QueueQuant
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn't tell you what to do about it. That's what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose