Heathland 132/33kV Substation
South Scotland, SP Energy Networks
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Heathland Wind Farm | EDF ENERGY RENEWABLES LIMITED | Storage with solar or wind | 80 | 29 Sep 2028 | Not stated | Scoping |
Recent changes
- Heathland Wind FarmSouth Scotland, Storage with solar or windConnection date moved from 31 Mar 2027 to 29 Sep 2028 (+18 months)+18 mo
- Heathland Wind FarmSouth Scotland, Storage with solar or windTechnology changed from Onshore wind to Storage, Onshore wind
- Heathland Wind FarmSouth Scotland, Storage with solar or windConnection point changed from Heathland Wind Farm 132/33kV Substation to Heathland 132/33kV Substation
- Heathland Wind FarmSouth Scotland, Storage with solar or windCapacity changed from 84 MW to 80 MW
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?