Heathland Wind Farm
EDF ENERGY RENEWABLES LIMITED at Heathland 132/33kV Substation
- Connection date
- 29 Sep 2028
- Gate
- Not stated
- Status
- Scoping
- Technology
- Storage + Onshore wind
- Total capacity
- 80 MW
- Connected now
- 0 MW
- Still to connect
- 80 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-001156
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 27 Jun 2025 registerConnection date moved from 31 Mar 2027 to 29 Sep 2028 (+18 months)
- 27 Sep 2024 registerTechnology changed from Onshore wind to Storage, Onshore wind
- 23 Dec 2022 registerConnection point changed from Heathland Wind Farm 132/33kV Substation to Heathland 132/33kV Substation
- 28 May 2021 registerCapacity changed from 84 MW to 80 MW
Also at Heathland 132/33kV Substation
Substation viewNo other projects in the register at this connection point.