Correen Hills Wind Farm
EDF ENERGY RENEWABLES LIMITED at Correen Hills Wind Farm 132kV Substation
- Connection date
- 30 Sep 2031
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Onshore wind
- Total capacity
- 68.4 MW
- Connected now
- 0 MW
- Still to connect
- 68.4 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-001825
- In the register since
- April 2023
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 14 Apr 2026 registerMarked as Gate 1
- 29 Aug 2025 registerConnection point changed from Littlewoods Wind Farm 132/33kV Substation to Correen Hills Wind Farm 132kV Substation
- 29 Jul 2025 registerRenamed from Littlewoods Wind Farm
- 27 Jun 2025 registerConnection date moved from 28 Sep 2029 to 30 Sep 2031 (+24 months)
- 28 Feb 2025 registerConnection date moved from 31 Aug 2028 to 28 Sep 2029 (+13 months)
- 28 Jun 2024 registerSubstation name updated in the register (from Littlewoods Wind Farm 132/33kV to Littlewoods Wind Farm 132/33kV Substation)
- 28 Jun 2024 registerTransmission owner changed from NGET to SHET
- 31 May 2024 registerTransmission owner changed from SHET to NGET
- 28 Apr 2023 registerAdded to the register
Also at Correen Hills Wind Farm 132kV Substation
Substation viewNo other projects in the register at this connection point.