Dunside Wind Farm (Formally Fallago Rig 2 Wind Farm)
- Connection date
- 30 Apr 2029
- Gate
- Not stated
- Status
- Awaiting Consents
- Technology
- Onshore wind
- Total capacity
- 100 MW
- Connected now
- 0 MW
- Still to connect
- 100 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-000526
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 16 Dec 2025 registerRenamed from Dunside Wind Farm
- 29 Jul 2025 registerRenamed from Fallago Rig 2
- 29 Oct 2024 registerConnection date moved from 30 Apr 2028 to 30 Apr 2029 (+12 months)
- 27 Sep 2024 registerConnection point changed from Fallago 400kV Substation to Fallago 400/33kV
- 31 May 2024 registerConnection date moved from 30 Jan 2028 to 30 Apr 2028 (+3 months)
- 26 Mar 2024 registerConnection date moved from 31 Jan 2028 to 30 Jan 2028 (1 day earlier)
- 30 Jan 2024 registerConnection date moved from 31 Oct 2023 to 31 Jan 2028 (+51 months)
- 31 Oct 2023 registerCapacity changed from 41.4 MW to 100 MW
Also at Fallago 400/33kV
Substation view2 other projects, 150 MW still to connect at this substation in total.