Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / South Scotland

Cloich Forest Wind Farm

EDF ENERGY RENEWABLES LIMITED at Cloich 132kV Substation

Connection date
31 Jul 2029
Gate
Not stated
Status
Scoping
Technology
Onshore wind
Total capacity
67.2 MW
Connected now
0 MW
Still to connect
67.2 MW
Transmission owner
SP Energy Networks (SPT)
Agreement type
Direct Connection
Region
South Scotland
Project number
PRO-001387
In the register since
March 2021

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 12 Dec 2025 register
    Transmission owner changed from SHET to SPT
  • 29 Jul 2025 register
    Connection point changed from Cloiche 132kV Substation to Cloich 132kV Substation
  • 24 Dec 2024 register
    Connection date moved from 30 Jul 2028 to 31 Jul 2029 (+12 months)
  • 24 Dec 2024 register
    Transmission owner changed from SPT to SHET
  • 23 Dec 2022 register
    Substation name updated in the register (from Cloiche 132kV to Cloiche 132kV Substation)
  • 28 May 2021 register
    Connection point changed from Currie to Cloiche 132kV
  • 30 Mar 2021 register
    Added to the register

Also at Cloich 132kV Substation

Substation view

No other projects in the register at this connection point.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO