Garn Fach Wind Farm
EDF ENERGY RENEWABLES LIMITED at MID WALES CONNECTION NODE A 400KV SUBSTATION
- Connection date
- 31 Oct 2037
- Gate
- Not stated
- Status
- Scoping
- Technology
- Storage + Onshore wind
- Total capacity
- 162 MW
- Connected now
- 0 MW
- Still to connect
- 162 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001157
- In the register since
- December 2021
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 29 Aug 2025 registerConnection point changed from Garn Fach 132kV Substation to MID WALES CONNECTION NODE A 400KV SUBSTATION
- 27 Jun 2025 registerCapacity changed from 110 MW to 162 MW
- 27 Jun 2025 registerConnection date moved from 1 May 2032 to 31 Oct 2037 (+66 months)
- 27 Jun 2025 registerTechnology changed from Onshore wind to Storage, Onshore wind
- 31 Dec 2021 registerAdded to the register
Also at MID WALES CONNECTION NODE A 400KV SUBSTATION
Substation view3 other projects, 799 MW still to connect at this substation in total. 100 MW is due to connect here before this project’s connection date of 31 Oct 2037.