Fallago 400/33kV
South Scotland, SP Energy Networks
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Dunside Wind Farm (Formally Fallago Rig 2 Wind Farm) | EDF ENERGY RENEWABLES LIMITED | Onshore wind | 100 | 30 Apr 2029 | Not stated | Awaiting Consents |
| Shielburn Energy Park | SUNLAWS DEVELOPMENT COMPANY LIMITED | Storage | 49.5 | 30 Apr 2033 | Gate 1 | Scoping |
| Fallago Rig Wind Farm | FALLAGO RIG WINDFARM LIMITED | Onshore wind | 0 | Connected | Not stated | Built |
Recent changes
- Shielburn Energy ParkSouth Scotland, StorageMarked as Gate 1
- Dunside Wind Farm (Formally Fallago Rig 2 Wind Farm)South Scotland, Onshore windRenamed from Dunside Wind Farm
- Dunside Wind Farm (Formally Fallago Rig 2 Wind Farm)South Scotland, Onshore windRenamed from Fallago Rig 2
- Shielburn Energy ParkSouth Scotland, StorageAdded to the registerNew
- Dunside Wind Farm (Formally Fallago Rig 2 Wind Farm)South Scotland, Onshore windConnection date moved from 30 Apr 2028 to 30 Apr 2029 (+12 months)+12 mo
- Dunside Wind Farm (Formally Fallago Rig 2 Wind Farm)South Scotland, Onshore windConnection point changed from Fallago 400kV Substation to Fallago 400/33kV
- Fallago Rig Wind FarmSouth Scotland, Onshore windConnection point changed from Fallago 400kV Substation to Fallago 400/33kV
- Dunside Wind Farm (Formally Fallago Rig 2 Wind Farm)South Scotland, Onshore windConnection date moved from 30 Jan 2028 to 30 Apr 2028 (+3 months)+3 mo
- Dunside Wind Farm (Formally Fallago Rig 2 Wind Farm)South Scotland, Onshore windConnection date moved from 31 Jan 2028 to 30 Jan 2028 (1 day earlier)
- Dunside Wind Farm (Formally Fallago Rig 2 Wind Farm)South Scotland, Onshore windConnection date moved from 31 Oct 2023 to 31 Jan 2028 (+51 months)+51 mo
- Dunside Wind Farm (Formally Fallago Rig 2 Wind Farm)South Scotland, Onshore windCapacity changed from 41.4 MW to 100 MW
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose