Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Lightsource Renewable UK Development Limited

Customer named in the TEC register

35projects in the register
8.5 GWstill to connect
0 MWof that with Gate 2 offers
0 MWconnected now

Projects

ProjectConnection siteTechnologyQueued MWConnection dateGateStatus
Walton Road Energy ProjectDrakelow 400kV SubstationStorage with solar or wind24031 Oct 2029Gate 1Scoping
Lightsource ThreepwoodGala North 400/132kV SubstationStorage15031 Oct 2030Gate 1Scoping
Lightsource Mount Annan BESSChapelcross 132/33kVStorage15031 Oct 2031Not statedScoping
Lightsource AuchansLinwood 400kV SubstationStorage40028 Oct 2033Gate 1Scoping
Lightsource Bramford PV & BESSSouth Anglia Connection Node A 400kV SubstationStorage with solar or wind24030 Oct 2034Gate 1Scoping
Lightsource Jubilee FarmJubilee Farm 275kV SubstationStorage with solar or wind24030 Oct 2034Gate 1Scoping
Lightsource BraybrookeWest Anglia Connection Node F 400kV SubstationStorage with solar or wind24031 Oct 2034Gate 1Scoping
Lightsource Grendon PV+BESSWest Anglia Connection Node C 400kV SubstationStorage with solar or wind24031 Oct 2034Not statedScoping
Lightsource Marston Vale 240MW PV+BESSMarston Vale 400kV SubstationStorage with solar or wind24031 Oct 2034Gate 1Scoping
Lightsource Yaxley PVNorth Anglia Connection Node E 400kV SubstationStorage with solar or wind24031 Oct 2034Gate 1Scoping
Lightsource Hawthorne PitWearside Connection Node B 400kV SubstationStorage with solar or wind24030 Oct 2035Gate 1Scoping
Lightsource New EggboroughLeeds North Connection Node B 400kV SubstationStorage with solar or wind24030 Oct 2035Gate 1Scoping
Lightsource Norton East PVNorton East 400kV SubstationStorage with solar or wind24030 Oct 2035Gate 1Scoping
Lightsource OffertonWearside Connection Node B 2 400kV SubstationStorage with solar or wind24030 Oct 2035Gate 1Scoping
Lightsource OvertonNorth Humber Connection Node E 400kV SubstationStorage with solar or wind24030 Oct 2035Gate 1Scoping
Bargatton Farm BESSBargatton Farm BESS 132kV SubstationStorage10031 Oct 2036Gate 1Scoping
Lightsource Bagots FarmDerbyshire Connection Node E 400kV SubstationStorage with solar or wind24030 Oct 2037Gate 1Scoping
Lightsource BodelwyddanCheshire Connection Node B 400kV SubstationStorage30030 Oct 2037Gate 1Scoping
Lightsource Enderby PV+BESSDerbyshire Connection Node B 400kV SubstationStorage with solar or wind24030 Oct 2037Gate 1Scoping
Lightsource Lower FranktonCheshire Connection Node A 400kV SubstationStorage with solar or wind24030 Oct 2037Gate 1Scoping
Lightsource MiddletonMiddleton 400KV SubstationStorage with solar or wind24030 Oct 2037Gate 1Scoping
Lightsource Patford BridgeDerbyshire Connection Node I 400kV SubstationStorage with solar or wind24030 Oct 2037Gate 1Scoping
Lightsource PyworthyWest Country Connection Node A 400kV SubstationStorage30030 Oct 2037Gate 1Scoping
Lightsource Shipley PVSussex and Romney Connection Node B 400kV SubstationStorage with solar or wind24030 Oct 2037Gate 1Scoping
Lightsource WillingtonDerbyshire Connection Node D 400kV SubstationStorage with solar or wind24030 Oct 2037Gate 1Scoping
Lightsourcebp Amlwch BESS and HydrogenWylfa South 400kV SubstationStorage60030 Oct 2037Gate 1Scoping
Lightsourcebp Wakeleys Wind and BESSDerbyshire Connection Node G 400kVStorage with solar or wind24030 Oct 2037Not statedScoping
Little HorstedSussex and Romney Connection Node A 400kV SubstationStorage with solar or wind5730 Oct 2037Gate 1Scoping
Lightsource BerthlwydMID WALES CONNECTION NODE A 400KV SUBSTATIONStorage with solar or wind24031 Oct 2037Gate 1Scoping
Lightsource Folly FarmSevern Connection Node A 400kv SubstationStorage with solar or wind24031 Oct 2037Gate 1Scoping
Lightsource Newchurch PV/BESSEast Kent connection node A 400kV SubstationStorage with solar or wind24031 Oct 2037Not statedScoping
Lightsource Rhigos BESSSouth Wales West Connection Node A 400kV SubstationStorage30031 Oct 2037Not statedScoping
SwainsthorpeNorth Anglia Connection Node A 400kVStorage with solar or wind30031 Oct 2037Gate 1Scoping
Brentford (SSEN-FBT624) -120MW BESSWest London Connection Node B 132kV substationStorage12031 Oct 2038Gate 1Scoping
Lightsource Ferryside PVSouth Wales West Connection Node C 400kVStorage with solar or wind24031 Oct 2038 +12 moGate 1Scoping

Left the register since January 2021: Lightsource Chirk (240 MW).

Recent changes

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO