Wearside Connection Node B 400kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Hawthorn BESS | REWE 8 LIMITED | Storage | 200 | 30 Oct 2035 +24 mo | Gate 1 | Awaiting Consents |
| Lightsource Hawthorne Pit | Lightsource Renewable UK Development Limited | Storage with solar or wind | 240 | 30 Oct 2035 | Gate 1 | Scoping |
| NatPower Hawthorn Pit Green Energy Park | NP SPV 29 LIMITED | Storage | 1,000 | 30 Oct 2035 | Not stated | Scoping |
| Noventum Hawthorn Pit | NOVENTUM POWER SOLAR 2 LIMITED | Storage with solar or wind | 57 | 30 Oct 2035 | Gate 1 | Scoping |
| Zenobe Hawthorn Pit BESS | ZENOBE ENERGY LIMITED | Storage | 300 | 30 Oct 2035 −24 mo | Gate 1 | Scoping |
Recent changes
- Noventum Hawthorn PitEngland and Wales, Storage with solar or windMarked as Gate 1
- Hawthorn BESSEngland and Wales, StorageConnection date moved from 31 Oct 2033 to 30 Oct 2035 (+24 months)+24 mo
- Zenobe Hawthorn Pit BESSEngland and Wales, StorageConnection date moved from 31 Oct 2037 to 30 Oct 2035 (−24 months)−24 mo
- Hawthorn BESSEngland and Wales, StorageConnection point changed from Hawthorn Pit 400kV Substation to Wearside Connection Node B 400kV Substation
- Hawthorn BESSEngland and Wales, StorageMarked as Gate 1
- Zenobe Hawthorn Pit BESSEngland and Wales, StorageMarked as Gate 1
- Lightsource Hawthorne PitEngland and Wales, Storage with solar or windConnection point changed from Hawthorn Pit 400kV Substation to Wearside Connection Node B 400kV Substation
- Lightsource Hawthorne PitEngland and Wales, Storage with solar or windMarked as Gate 1
- Zenobe Hawthorn Pit BESSEngland and Wales, StorageConnection point changed from Hawthorn Pit 400kV Substation to Wearside Connection Node B 400kV Substation
- NatPower Hawthorn Pit Green Energy ParkEngland and Wales, StorageConnection point changed from Hawthorn Pit 400kV Substation to Wearside Connection Node B 400kV Substation
- NatPower Hawthorn Pit Green Energy ParkEngland and Wales, StorageAdded to the registerNew
- Noventum Hawthorn PitEngland and Wales, Storage with solar or windConnection point changed from Hawthorn Pit 400kV Substation to Wearside Connection Node B 400kV Substation
- Noventum Hawthorn PitEngland and Wales, Storage with solar or windConnection date moved from 31 Oct 2033 to 30 Oct 2035 (+24 months)+24 mo
- Hawthorn BESSEngland and Wales, StorageCustomer changed from CSWE 8 LIMITED to REWE 8 LIMITED
- Zenobe Hawthorn Pit BESSEngland and Wales, StorageAdded to the registerNew
- Lightsource Hawthorne PitEngland and Wales, Storage with solar or windAdded to the registerNew
- Noventum Hawthorn PitEngland and Wales, Storage with solar or windAdded to the registerNew
- Hawthorn BESSEngland and Wales, StorageAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose