Lightsource Ferryside PV
Lightsource Renewable UK Development Limited at South Wales West Connection Node C 400kV
- Connection date
- 31 Oct 2038 +12 months since 9 Dec
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage + Solar
- Total capacity
- 240 MW
- Connected now
- 0 MW
- Still to connect
- 240 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-003761
- In the register since
- December 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 16 Oct 2026 registerConnection date moved from 30 Oct 2038 to 31 Oct 2038 (1 day later)
- 10 Oct 2026 registerConnection date moved from 30 Oct 2037 to 30 Oct 2038 (+12 months)
- 17 Mar 2026 registerMarked as Gate 1
- 30 Jul 2024 registerConnection point changed from Llandyfaelog 400/132kV Substation to South Wales West Connection Node C 400kV
- 31 May 2024 registerConnection point changed from Llandefaelog 400kV Substation to Llandyfaelog 400/132kV Substation
- 26 Apr 2024 registerConnection point changed from Carmarthen 400kV Substation to Llandefaelog 400kV Substation
- 29 Dec 2023 registerAdded to the register
Also at South Wales West Connection Node C 400kV
Substation view1 other project, 288 MW still to connect at this substation in total. 47.5 MW is due to connect here before this project’s connection date of 31 Oct 2038.