Projects / Substation

North Anglia Connection Node A 400kV

England and Wales, National Grid Electricity Transmission

6projects in the register
2.9 GWstill to connect
0 MWof that with Gate 2 offers
0 MWconnected now

The queue at this substation

ProjectCustomerTechnologyQueued MWConnection dateGateStatus
GF Norwich BESSGF Norwich Energy LtdStorage40031 Oct 2032Gate 1Scoping
Norwich Main BESSTASWAY ENERGY PARK LIMITEDStorage with solar or wind95031 Oct 2032Gate 1Scoping
Long Stratton 400ENSO GREEN HOLDINGS X LIMITEDStorage with solar or wind40031 Oct 2034Gate 1Scoping
Long Stratton BESSField Long Stratton LtdStorage40031 Oct 2034Gate 1Scoping
Noventum -Long StrattonNoventum Power Solar 8 LimitedStorage with solar or wind46031 Oct 2034Gate 1Scoping
SwainsthorpeLightsource Renewable UK Development LimitedStorage with solar or wind30031 Oct 2037Gate 1Scoping

Left the register since tracking began: Elmya Gissing BESS & PV (900 MW).

Recent changes

  • Elmya Gissing BESS & PVEngland and Wales, Storage with solar or windLeft the register (900 MW from 31 Oct 2034)900 MW
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn't tell you what to do about it. That's what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose