Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / Substation

Wylfa South 400kV Substation

England and Wales, National Grid Electricity Transmission

3projects in the register
1.1 GWstill to connect
0 MWof that with Gate 2 offers
0 MWconnected now

The queue at this substation

ProjectCustomerTechnologyQueued MWConnection dateGateStatus
Mon Solar FarmLIGHTSOURCE SPV 204 LIMITEDStorage with solar or wind36030 Oct 2029Not statedScoping
Lightsourcebp Amlwch BESS and HydrogenLightsource Renewable UK Development LimitedStorage60030 Oct 2037Gate 1Scoping
Lightsource Mon Solar 2LIGHTSOURCE SPV 204 LIMITEDStorage with solar or wind12030 Nov 2037Gate 1Scoping

Recent changes

  • Lightsource Mon Solar 2England and Wales, Storage with solar or windMarked as Gate 1
  • Lightsourcebp Amlwch BESS and HydrogenEngland and Wales, StorageMarked as Gate 1
  • Mon Solar FarmEngland and Wales, Storage with solar or windRestructured from 1 stage (240 MW from 31 Oct 2028) to 2 stages (240 MW from 30 Oct 2029, 120 MW from 30 Oct 2037). First connection date +12 months+12 mo
  • Lightsourcebp Amlwch BESS and HydrogenEngland and Wales, StorageConnection date moved from 31 Oct 2037 to 30 Oct 2037 (1 day earlier)
  • Mon Solar FarmEngland and Wales, Storage with solar or windConnection point changed from Wylfa 400kV Substation to Wylfa South 400kV Substation
  • Lightsourcebp Amlwch BESS and HydrogenEngland and Wales, StorageAdded to the registerNew
  • Mon Solar FarmEngland and Wales, Storage with solar or windConnection date moved from 31 Oct 2026 to 31 Oct 2028 (+24 months)+24 mo
  • Lightsource Mon Solar 2England and Wales, Storage with solar or windAdded to the registerNew
  • Mon Solar FarmEngland and Wales, Storage with solar or windSubstation name updated in the register (from Wylfa 400kV to Wylfa 400kV Substation)
  • Mon Solar FarmEngland and Wales, Storage with solar or windCapacity changed from 480 MW to 240 MW
  • Mon Solar FarmEngland and Wales, Storage with solar or windAdded to the registerNew
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO