Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / Substation

West Anglia Connection Node F 400kV Substation

England and Wales, National Grid Electricity Transmission

6projects in the register
3.4 GWstill to connect
0 MWof that with Gate 2 offers
0 MWconnected now

The queue at this substation

ProjectCustomerTechnologyQueued MWConnection dateGateStatus
Lightsource BraybrookeLightsource Renewable UK Development LimitedStorage with solar or wind24031 Oct 2034Gate 1Scoping
Little HarrowdenLittle Harrowden 10 Renewables LimitedSolar1,00031 Oct 2034Not statedScoping
Market HarboroughCONNECTID 1 LIMITEDStorage with solar or wind70031 Oct 2034Not statedAwaiting Consents
Market Harborough Green Energy HubTELIS ENERGY UK LIMITEDMulti-technology hub1,00031 Oct 2034Gate 1Scoping
Nethercourt Solar & BESS FarmGreentech Invest UK (15) LimitedStorage with solar or wind24031 Oct 2034Gate 1Scoping
Noventum Market HarboroughNOVENTUM POWER SOLAR 1 LIMITEDStorage with solar or wind24931 Oct 2034Gate 1Scoping

Recent changes

  • Market Harborough Green Energy HubEngland and Wales, Multi-technology hubMarked as Gate 1
  • Market HarboroughEngland and Wales, Storage with solar or windStatus changed from Scoping to Awaiting Consents
  • Nethercourt Solar & BESS FarmEngland and Wales, Storage with solar or windMarked as Gate 1
  • Noventum Market HarboroughEngland and Wales, Storage with solar or windMarked as Gate 1
  • Lightsource BraybrookeEngland and Wales, Storage with solar or windMarked as Gate 1
  • Market Harborough Green Energy HubEngland and Wales, Multi-technology hubConnection point changed from Market Harborough 400kV Substation to West Anglia Connection Node F 400kV Substation
  • Nethercourt Solar & BESS FarmEngland and Wales, Storage with solar or windCustomer changed from GREENTECH PROJECTS HOLDING UK LIMITED to Greentech Invest UK (15) Limited
  • Nethercourt Solar & BESS FarmEngland and Wales, Storage with solar or windCustomer changed from Greentech Services Limited to GREENTECH PROJECTS HOLDING UK LIMITED
  • Nethercourt Solar & BESS FarmEngland and Wales, Storage with solar or windCustomer changed from GREENTECH PROJECTS HOLDING UK LIMITED to Greentech Services Limited
  • Nethercourt Solar & BESS FarmEngland and Wales, Storage with solar or windConnection point changed from Nethercourt Substation to West Anglia Connection Node F 400kV Substation
  • Little HarrowdenEngland and Wales, SolarConnection date moved from 31 Oct 2032 to 31 Oct 2034 (+24 months)+24 mo
  • Lightsource BraybrookeEngland and Wales, Storage with solar or windConnection point changed from Braybrooke 400kV Substation to West Anglia Connection Node F 400kV Substation
  • Lightsource BraybrookeEngland and Wales, Storage with solar or windConnection date moved from 30 Oct 2036 to 31 Oct 2034 (−24 months)−24 mo
  • Nethercourt Solar & BESS FarmEngland and Wales, Storage with solar or windConnection date moved from 31 Oct 2035 to 31 Oct 2034 (−12 months)−12 mo
  • Market HarboroughEngland and Wales, Storage with solar or windConnection point changed from Market Harborough 400kV Substation to West Anglia Connection Node F 400kV Substation
  • Market HarboroughEngland and Wales, Storage with solar or windCapacity changed from 1,200 MW to 700 MW
  • Little HarrowdenEngland and Wales, SolarConnection point changed from Little Harrowden 400kV to West Anglia Connection Node F 400kV Substation
  • Noventum Market HarboroughEngland and Wales, Storage with solar or windConnection point changed from Market Harborough 400kV Substation to West Anglia Connection Node F 400kV Substation
  • Noventum Market HarboroughEngland and Wales, Storage with solar or windConnection date moved from 31 Oct 2031 to 31 Oct 2034 (+36 months)+36 mo
  • Little HarrowdenEngland and Wales, SolarConnection point changed from Grendon 400kV Substation to Little Harrowden 400kV
  • Little HarrowdenEngland and Wales, SolarCustomer changed from ORRÖN ENERGY DEVELOPMENT LIMITED to Little Harrowden 10 Renewables Limited
  • Little HarrowdenEngland and Wales, SolarConnection point changed from Little Harrowden 400kV to Grendon 400kV Substation
  • Nethercourt Solar & BESS FarmEngland and Wales, Storage with solar or windAdded to the registerNew
  • Lightsource BraybrookeEngland and Wales, Storage with solar or windAdded to the registerNew
  • Market Harborough Green Energy HubEngland and Wales, Multi-technology hubConnection point changed from Thorpe Underwood 400kV to Market Harborough 400kV Substation
  • Market Harborough Green Energy HubEngland and Wales, Multi-technology hubTechnology changed from Storage, Nuclear, Solar, Onshore wind to Storage, Hydro, Nuclear, Solar, Onshore wind
  • Noventum Market HarboroughEngland and Wales, Storage with solar or windAdded to the registerNew
  • Market HarboroughEngland and Wales, Storage with solar or windAdded to the registerNew
  • Market Harborough Green Energy HubEngland and Wales, Multi-technology hubAdded to the registerNew
  • Little HarrowdenEngland and Wales, SolarAdded to the registerNew
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO