North Humber Connection Node E 400kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Natpower Upsall Green Energy Park | BELLMOOR ENERGY PARK LIMITED | Storage | 1,000 | 31 Oct 2033 | Gate 1 | Scoping |
| Lightsource Overton | Lightsource Renewable UK Development Limited | Storage with solar or wind | 240 | 30 Oct 2035 | Gate 1 | Scoping |
| OVERTON440MW BESS | CARE POWER (OVERTON) LIMITED | Storage | 440 | 30 Oct 2035 | Not stated | Scoping |
Recent changes
- Lightsource OvertonEngland and Wales, Storage with solar or windMarked as Gate 1
- Natpower Upsall Green Energy ParkEngland and Wales, StorageMarked as Gate 1
- OVERTON440MW BESSEngland and Wales, StorageCustomer changed from SMS ENERGY SERVICES LIMITED to CARE POWER (OVERTON) LIMITED
- Natpower Upsall Green Energy ParkEngland and Wales, StorageCustomer changed from NP SPV 21 LIMITED to BELLMOOR ENERGY PARK LIMITED
- Natpower Upsall Green Energy ParkEngland and Wales, StorageConnection point changed from Upsall 400kV substation to North Humber Connection Node E 400kV Substation
- OVERTON440MW BESSEngland and Wales, StorageConnection point changed from Overton IDNO GSP to North Humber Connection Node E 400kV Substation
- OVERTON440MW BESSEngland and Wales, StorageConnection date moved from 31 Oct 2035 to 30 Oct 2035 (1 day earlier)
- Lightsource OvertonEngland and Wales, Storage with solar or windConnection date moved from 30 Oct 2036 to 30 Oct 2035 (−12 months)−12 mo
- Lightsource OvertonEngland and Wales, Storage with solar or windConnection point changed from Overton 400kV Substation to North Humber Connection Node E 400kV Substation
- OVERTON440MW BESSEngland and Wales, StorageAdded to the registerNew
- Lightsource OvertonEngland and Wales, Storage with solar or windAdded to the registerNew
- Natpower Upsall Green Energy ParkEngland and Wales, StorageAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?