Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

ENSO GREEN HOLDINGS X LIMITED

Customer named in the TEC register

12projects in the register
5.4 GWstill to connect
0 MWof that with Gate 2 offers
0 MWconnected now

Projects

ProjectConnection siteTechnologyQueued MWConnection dateGateStatus
CilfynyddCilfynydd 400kV SubstationStorage with solar or wind40031 Oct 2030Gate 1Awaiting Consents
StaythorpeStaythorpe 400kV SubstationStorage with solar or wind40031 Oct 2030Gate 1Scoping
Monk FrystonMonk Fryston 400kV SubstationStorage with solar or wind40031 Oct 2031Gate 1Scoping
NortonNorton East 400kV SubstationStorage with solar or wind40031 Oct 2032Gate 1Scoping
Exeter MainExeter 400kV SubstationStorage with solar or wind40028 Oct 2033Gate 1Scoping
CellarheadCellarhead 400kV SubstationStorage with solar or wind40031 Oct 2033Gate 1Scoping
High Marnham 400High Marnham 400kV SubstationStorage with solar or wind1,00031 Oct 2033Not statedAwaiting Consents
Long Stratton 400North Anglia Connection Node A 400kVStorage with solar or wind40031 Oct 2034Gate 1Scoping
Pelham 400West Anglia Connection Node E 400kV SubstationStorage with solar or wind40031 Oct 2034Gate 1Scoping
FeckenhamFeckenham 400kV SubstationStorage with solar or wind40031 Oct 2036Gate 1Awaiting Consents
ChickerellChickerell 400kV SubstationStorage with solar or wind4006 Dec 2036Gate 1Awaiting Consents
Langage 400Langage 400kV SubstationStorage with solar or wind40019 Dec 2036Gate 1Scoping

Recent changes

  • CellarheadEngland and Wales, Storage with solar or windConnection date moved from 31 Oct 2031 to 31 Oct 2033 (+24 months)+24 mo
  • Pelham 400England and Wales, Storage with solar or windConnection date moved from 30 Oct 2033 to 31 Oct 2034 (+12 months)+12 mo
  • CellarheadEngland and Wales, Storage with solar or windConnection date moved from 31 Oct 2033 to 31 Oct 2031 (−24 months)−24 mo
  • Pelham 400England and Wales, Storage with solar or windConnection date moved from 31 Oct 2034 to 30 Oct 2033 (−12 months)−12 mo
  • FeckenhamEngland and Wales, Storage with solar or windMarked as Gate 1
  • Monk FrystonEngland and Wales, Storage with solar or windMarked as Gate 1
  • Pelham 400England and Wales, Storage with solar or windMarked as Gate 1
  • StaythorpeEngland and Wales, Storage with solar or windMarked as Gate 1
  • CellarheadEngland and Wales, Storage with solar or windMarked as Gate 1
  • Pelham 400England and Wales, Storage with solar or windConnection point changed from Pelham 400kV Substation to West Anglia Connection Node E 400kV Substation
  • ChickerellEngland and Wales, Storage with solar or windStage 1: Marked as Gate 1
  • ChickerellEngland and Wales, Storage with solar or windStage 2: Marked as Gate 1
  • ChickerellEngland and Wales, Storage with solar or windStage 3: Marked as Gate 1
  • CilfynyddEngland and Wales, Storage with solar or windMarked as Gate 1
  • Exeter MainEngland and Wales, Storage with solar or windMarked as Gate 1
  • Langage 400England and Wales, Storage with solar or windStage 1: Marked as Gate 1
  • Langage 400England and Wales, Storage with solar or windStage 2: Marked as Gate 1
  • Langage 400England and Wales, Storage with solar or windStage 3: Marked as Gate 1
  • Long Stratton 400England and Wales, Storage with solar or windMarked as Gate 1
  • NortonEngland and Wales, Storage with solar or windCustomer changed from ENSO GREEN HOLDINGS LIMITED to ENSO GREEN HOLDINGS X LIMITED
  • NortonEngland and Wales, Storage with solar or windMarked as Gate 1
  • NortonEngland and Wales, Storage with solar or windConnection point changed from Norton 400kV Substation to Norton East 400kV Substation
  • CellarheadEngland and Wales, Storage with solar or windCustomer changed from ENSO GREEN HOLDINGS LIMITED to ENSO GREEN HOLDINGS X LIMITED
  • Exeter MainEngland and Wales, Storage with solar or windCustomer changed from ENSO GREEN HOLDINGS LIMITED to ENSO GREEN HOLDINGS X LIMITED
  • FeckenhamEngland and Wales, Storage with solar or windCustomer changed from ENSO GREEN HOLDINGS LIMITED to ENSO GREEN HOLDINGS X LIMITED
  • FeckenhamEngland and Wales, Storage with solar or windTechnology changed from Storage, Solar to Demand, Storage, Solar
  • High Marnham 400England and Wales, Storage with solar or windCustomer changed from ENSO GREEN HOLDINGS LIMITED to ENSO GREEN HOLDINGS X LIMITED
  • Langage 400England and Wales, Storage with solar or windCustomer changed from ENSO GREEN HOLDINGS LIMITED to ENSO GREEN HOLDINGS X LIMITED
  • Monk FrystonEngland and Wales, Storage with solar or windCustomer changed from ENSO GREEN HOLDINGS LIMITED to ENSO GREEN HOLDINGS X LIMITED
  • StaythorpeEngland and Wales, Storage with solar or windCustomer changed from ENSO GREEN HOLDINGS LIMITED to ENSO GREEN HOLDINGS X LIMITED
  • ChickerellEngland and Wales, Storage with solar or windCustomer changed from ENSO GREEN HOLDINGS LIMITED to ENSO GREEN HOLDINGS X LIMITED
  • CilfynyddEngland and Wales, Storage with solar or windCustomer changed from ENSO GREEN HOLDINGS LIMITED to ENSO GREEN HOLDINGS X LIMITED
  • Pelham 400England and Wales, Storage with solar or windAdded to the registerNew
  • High Marnham 400England and Wales, Storage with solar or windNew stage added (600 MW from 31 Oct 2034)
  • Exeter MainEngland and Wales, Storage with solar or windConnection date moved from 24 Nov 2031 to 28 Oct 2033 (+23 months)+23 mo
  • FeckenhamEngland and Wales, Storage with solar or windConnection date moved from 31 Jul 2036 to 31 Oct 2036 (+3 months)+3 mo
  • Long Stratton 400England and Wales, Storage with solar or windAdded to the registerNew
  • FeckenhamEngland and Wales, Storage with solar or windStage 1: Capacity changed from 200 MW to 400 MW
  • FeckenhamEngland and Wales, Storage with solar or windStage 1: Connection date moved from 31 Oct 2033 to 31 Jul 2036 (+33 months)+33 mo
  • FeckenhamEngland and Wales, Storage with solar or windStage removed (100 MW from 31 Oct 2034)
  • FeckenhamEngland and Wales, Storage with solar or windStage removed (100 MW from 31 Oct 2035)
  • High Marnham 400England and Wales, Storage with solar or windConnection point changed from High Marnham GSP to High Marnham 400kV Substation
  • CellarheadEngland and Wales, Storage with solar or windAdded to the registerNew
  • ChickerellEngland and Wales, Storage with solar or windAdded to the registerNew
  • CilfynyddEngland and Wales, Storage with solar or windAdded to the registerNew
  • Exeter MainEngland and Wales, Storage with solar or windAdded to the registerNew
  • FeckenhamEngland and Wales, Storage with solar or windAdded to the registerNew
  • High Marnham 400England and Wales, Storage with solar or windAdded to the registerNew
  • StaythorpeEngland and Wales, Storage with solar or windAdded to the registerNew
  • Monk FrystonEngland and Wales, Storage with solar or windAdded to the registerNew
  • NortonEngland and Wales, Storage with solar or windAdded to the registerNew
  • Langage 400England and Wales, Storage with solar or windAdded to the registerNew
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO