ENSO GREEN HOLDINGS X LIMITED
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Cilfynydd | Cilfynydd 400kV Substation | Storage with solar or wind | 400 | 31 Oct 2030 | Gate 1 | Awaiting Consents |
| Staythorpe | Staythorpe 400kV Substation | Storage with solar or wind | 400 | 31 Oct 2030 | Gate 1 | Scoping |
| Monk Fryston | Monk Fryston 400kV Substation | Storage with solar or wind | 400 | 31 Oct 2031 | Gate 1 | Scoping |
| Norton | Norton East 400kV Substation | Storage with solar or wind | 400 | 31 Oct 2032 | Gate 1 | Scoping |
| Exeter Main | Exeter 400kV Substation | Storage with solar or wind | 400 | 28 Oct 2033 | Gate 1 | Scoping |
| Cellarhead | Cellarhead 400kV Substation | Storage with solar or wind | 400 | 31 Oct 2033 | Gate 1 | Scoping |
| High Marnham 400 | High Marnham 400kV Substation | Storage with solar or wind | 1,000 | 31 Oct 2033 | Not stated | Awaiting Consents |
| Long Stratton 400 | North Anglia Connection Node A 400kV | Storage with solar or wind | 400 | 31 Oct 2034 | Gate 1 | Scoping |
| Pelham 400 | West Anglia Connection Node E 400kV Substation | Storage with solar or wind | 400 | 31 Oct 2034 | Gate 1 | Scoping |
| Feckenham | Feckenham 400kV Substation | Storage with solar or wind | 400 | 31 Oct 2036 | Gate 1 | Awaiting Consents |
| Chickerell | Chickerell 400kV Substation | Storage with solar or wind | 400 | 6 Dec 2036 | Gate 1 | Awaiting Consents |
| Langage 400 | Langage 400kV Substation | Storage with solar or wind | 400 | 19 Dec 2036 | Gate 1 | Scoping |
Recent changes
- CellarheadEngland and Wales, Storage with solar or windConnection date moved from 31 Oct 2031 to 31 Oct 2033 (+24 months)+24 mo
- Pelham 400England and Wales, Storage with solar or windConnection date moved from 30 Oct 2033 to 31 Oct 2034 (+12 months)+12 mo
- CellarheadEngland and Wales, Storage with solar or windConnection date moved from 31 Oct 2033 to 31 Oct 2031 (−24 months)−24 mo
- Pelham 400England and Wales, Storage with solar or windConnection date moved from 31 Oct 2034 to 30 Oct 2033 (−12 months)−12 mo
- FeckenhamEngland and Wales, Storage with solar or windMarked as Gate 1
- Monk FrystonEngland and Wales, Storage with solar or windMarked as Gate 1
- Pelham 400England and Wales, Storage with solar or windMarked as Gate 1
- StaythorpeEngland and Wales, Storage with solar or windMarked as Gate 1
- CellarheadEngland and Wales, Storage with solar or windMarked as Gate 1
- Pelham 400England and Wales, Storage with solar or windConnection point changed from Pelham 400kV Substation to West Anglia Connection Node E 400kV Substation
- ChickerellEngland and Wales, Storage with solar or windStage 1: Marked as Gate 1
- ChickerellEngland and Wales, Storage with solar or windStage 2: Marked as Gate 1
- ChickerellEngland and Wales, Storage with solar or windStage 3: Marked as Gate 1
- CilfynyddEngland and Wales, Storage with solar or windMarked as Gate 1
- Exeter MainEngland and Wales, Storage with solar or windMarked as Gate 1
- Langage 400England and Wales, Storage with solar or windStage 1: Marked as Gate 1
- Langage 400England and Wales, Storage with solar or windStage 2: Marked as Gate 1
- Langage 400England and Wales, Storage with solar or windStage 3: Marked as Gate 1
- Long Stratton 400England and Wales, Storage with solar or windMarked as Gate 1
- NortonEngland and Wales, Storage with solar or windCustomer changed from ENSO GREEN HOLDINGS LIMITED to ENSO GREEN HOLDINGS X LIMITED
- NortonEngland and Wales, Storage with solar or windMarked as Gate 1
- NortonEngland and Wales, Storage with solar or windConnection point changed from Norton 400kV Substation to Norton East 400kV Substation
- CellarheadEngland and Wales, Storage with solar or windCustomer changed from ENSO GREEN HOLDINGS LIMITED to ENSO GREEN HOLDINGS X LIMITED
- Exeter MainEngland and Wales, Storage with solar or windCustomer changed from ENSO GREEN HOLDINGS LIMITED to ENSO GREEN HOLDINGS X LIMITED
- FeckenhamEngland and Wales, Storage with solar or windCustomer changed from ENSO GREEN HOLDINGS LIMITED to ENSO GREEN HOLDINGS X LIMITED
- FeckenhamEngland and Wales, Storage with solar or windTechnology changed from Storage, Solar to Demand, Storage, Solar
- High Marnham 400England and Wales, Storage with solar or windCustomer changed from ENSO GREEN HOLDINGS LIMITED to ENSO GREEN HOLDINGS X LIMITED
- Langage 400England and Wales, Storage with solar or windCustomer changed from ENSO GREEN HOLDINGS LIMITED to ENSO GREEN HOLDINGS X LIMITED
- Monk FrystonEngland and Wales, Storage with solar or windCustomer changed from ENSO GREEN HOLDINGS LIMITED to ENSO GREEN HOLDINGS X LIMITED
- StaythorpeEngland and Wales, Storage with solar or windCustomer changed from ENSO GREEN HOLDINGS LIMITED to ENSO GREEN HOLDINGS X LIMITED
- ChickerellEngland and Wales, Storage with solar or windCustomer changed from ENSO GREEN HOLDINGS LIMITED to ENSO GREEN HOLDINGS X LIMITED
- CilfynyddEngland and Wales, Storage with solar or windCustomer changed from ENSO GREEN HOLDINGS LIMITED to ENSO GREEN HOLDINGS X LIMITED
- Pelham 400England and Wales, Storage with solar or windAdded to the registerNew
- High Marnham 400England and Wales, Storage with solar or windNew stage added (600 MW from 31 Oct 2034)
- Exeter MainEngland and Wales, Storage with solar or windConnection date moved from 24 Nov 2031 to 28 Oct 2033 (+23 months)+23 mo
- FeckenhamEngland and Wales, Storage with solar or windConnection date moved from 31 Jul 2036 to 31 Oct 2036 (+3 months)+3 mo
- Long Stratton 400England and Wales, Storage with solar or windAdded to the registerNew
- FeckenhamEngland and Wales, Storage with solar or windStage 1: Capacity changed from 200 MW to 400 MW
- FeckenhamEngland and Wales, Storage with solar or windStage 1: Connection date moved from 31 Oct 2033 to 31 Jul 2036 (+33 months)+33 mo
- FeckenhamEngland and Wales, Storage with solar or windStage removed (100 MW from 31 Oct 2034)
- FeckenhamEngland and Wales, Storage with solar or windStage removed (100 MW from 31 Oct 2035)
- High Marnham 400England and Wales, Storage with solar or windConnection point changed from High Marnham GSP to High Marnham 400kV Substation
- CellarheadEngland and Wales, Storage with solar or windAdded to the registerNew
- ChickerellEngland and Wales, Storage with solar or windAdded to the registerNew
- CilfynyddEngland and Wales, Storage with solar or windAdded to the registerNew
- Exeter MainEngland and Wales, Storage with solar or windAdded to the registerNew
- FeckenhamEngland and Wales, Storage with solar or windAdded to the registerNew
- High Marnham 400England and Wales, Storage with solar or windAdded to the registerNew
- StaythorpeEngland and Wales, Storage with solar or windAdded to the registerNew
- Monk FrystonEngland and Wales, Storage with solar or windAdded to the registerNew
- NortonEngland and Wales, Storage with solar or windAdded to the registerNew
- Langage 400England and Wales, Storage with solar or windAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?