Projects / Substation
Staythorpe 400kV Substation
England and Wales, National Grid Electricity Transmission
5projects in the register
1.9 GWstill to connect
0 MWof that with Gate 2 offers
1.8 GWconnected now
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Flash Solar Farm | ELEMENTS GREEN TRENT LTD | Storage with solar or wind | 800 | 31 May 2027 | Not stated | Consented |
| Staythorpe (BESS and PV) | SSE STAYTHORPE POWER LIMITED | Storage with solar or wind | 437 | 29 Sep 2028 | Not stated | Consented |
| Field Farm | Net Zero One Ltd | Storage | 250 | 31 Oct 2030 | Gate 1 | Scoping |
| Staythorpe | ENSO GREEN HOLDINGS X LIMITED | Storage with solar or wind | 400 | 31 Oct 2030 | Gate 1 | Scoping |
| Staythorpe C | RWE GENERATION UK PLC | Thermal (gas, biomass, waste) | 0 | Connected | Not stated | Built |
Recent changes
- Staythorpe (BESS and PV)England and Wales, Storage with solar or windStatus changed from Awaiting consent to Consented
QueueQuant
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn't tell you what to do about it. That's what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose