Feckenham 400kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Feckenham Greener Grid Park | Statkraft UK Ltd | Storage | 150 | 31 Oct 2028 | Gate 1 | Scoping |
| Feckenham | IGP SOLAR 14 LIMITED | Storage with solar or wind | 500 | 21 Jul 2029 | Not stated | Scoping |
| Feckenham Green Energy Centre | FECKENHAM GREEN NG LIMITED | Storage with solar or wind | 1,025 | 30 Oct 2032 | Not stated | Scoping |
| Boom Power Feckenham Generation Hub | Wheaten Hill BESS Limited | Storage with solar or wind | 400 | 31 Oct 2033 | Gate 1 | Scoping |
| Feckenham Energy Park | GREEN ENERGY MAB LTD | Storage | 500 | 31 Oct 2033 | Not stated | Scoping |
| Feckenham | ENSO GREEN HOLDINGS X LIMITED | Storage with solar or wind | 400 | 31 Oct 2036 | Gate 1 | Awaiting Consents |
| Feckenham PV & BESS Station | IB VOGT UK LTD | Storage with solar or wind | 400 | 30 Oct 2037 +48 mo | Gate 1 | Scoping |
Recent changes
- Feckenham PV & BESS StationEngland and Wales, Storage with solar or windConnection date moved from 31 Oct 2033 to 30 Oct 2037 (+48 months)+48 mo
- FeckenhamEngland and Wales, Storage with solar or windMarked as Gate 1
- Boom Power Feckenham Generation HubEngland and Wales, Storage with solar or windMarked as Gate 1
- Feckenham PV & BESS StationEngland and Wales, Storage with solar or windMarked as Gate 1
- Feckenham Greener Grid ParkEngland and Wales, StorageStage 1: Marked as Gate 1
- Feckenham Greener Grid ParkEngland and Wales, StorageStage 2: Marked as Gate 1
- Boom Power Feckenham Generation HubEngland and Wales, Storage with solar or windCustomer changed from BOOM POWER LTD to Wheaten Hill BESS Limited
- FeckenhamEngland and Wales, Storage with solar or windCustomer changed from ENSO GREEN HOLDINGS LIMITED to ENSO GREEN HOLDINGS X LIMITED
- FeckenhamEngland and Wales, Storage with solar or windTechnology changed from Storage, Solar to Demand, Storage, Solar
- Feckenham Green Energy CentreEngland and Wales, Storage with solar or windRenamed from Feckenham Green NG Limited
- Feckenham Green Energy CentreEngland and Wales, Storage with solar or windRenamed from Feckenham Green Energy Centre
- Feckenham Green Energy CentreEngland and Wales, Storage with solar or windTechnology changed from Storage, Solar to Demand, Storage, Solar
- Feckenham Greener Grid ParkEngland and Wales, StorageStage 1: Connection date moved from 31 Jan 2026 to 31 Oct 2028 (+33 months)+33 mo
- Feckenham Green Energy CentreEngland and Wales, Storage with solar or windCustomer changed from INNOVA RENEWABLES LIMITED to FECKENHAM GREEN NG LIMITED
- Feckenham Energy ParkEngland and Wales, StorageTechnology changed from Storage, Solar to Storage
- Feckenham Greener Grid ParkEngland and Wales, StorageStage 1: Technology changed from Storage, Reactive compensation to Storage
- Feckenham Greener Grid ParkEngland and Wales, StorageStage 2: Technology changed from Storage, Reactive compensation to Storage
- FeckenhamEngland and Wales, Storage with solar or windConnection date moved from 31 Jul 2036 to 31 Oct 2036 (+3 months)+3 mo
- FeckenhamEngland and Wales, Storage with solar or windStage 1: Capacity changed from 200 MW to 400 MW
- FeckenhamEngland and Wales, Storage with solar or windStage 1: Connection date moved from 31 Oct 2033 to 31 Jul 2036 (+33 months)+33 mo
- FeckenhamEngland and Wales, Storage with solar or windStage removed (100 MW from 31 Oct 2034)
- FeckenhamEngland and Wales, Storage with solar or windStage removed (100 MW from 31 Oct 2035)
- Feckenham PV & BESS StationEngland and Wales, Storage with solar or windAdded to the registerNew
- Feckenham Greener Grid ParkEngland and Wales, StorageStage 1: Connection date moved from 27 Oct 2023 to 31 Jan 2026 (+27 months)+27 mo
- Feckenham Greener Grid ParkEngland and Wales, StorageRenamed from Feckenham
- Boom Power Feckenham Generation HubEngland and Wales, Storage with solar or windAdded to the registerNew
- FeckenhamEngland and Wales, Storage with solar or windAdded to the registerNew
- Feckenham Energy ParkEngland and Wales, StorageAdded to the registerNew
- Feckenham Green Energy CentreEngland and Wales, Storage with solar or windCapacity changed from 400 MW to 1,025 MW
- Feckenham Green Energy CentreEngland and Wales, Storage with solar or windConnection date moved from 30 Oct 2028 to 30 Oct 2032 (+48 months)+48 mo
- Feckenham Greener Grid ParkEngland and Wales, StorageRestructured from 1 stage (12 MW from 30 Jun 2022) to 2 stages (12 MW from 27 Oct 2023, 138 MW from 31 Oct 2032). First connection date +16 months+16 mo
- FeckenhamEngland and Wales, Storage with solar or windSubstation name updated in the register (from Feckenham 400kV to Feckenham 400kV Substation)
- Feckenham Green Energy CentreEngland and Wales, Storage with solar or windSubstation name updated in the register (from Feckenham 400kV to Feckenham 400kV Substation)
- Feckenham Greener Grid ParkEngland and Wales, StorageSubstation name updated in the register (from Feckenham 400kV to Feckenham 400kV Substation)
- Feckenham Green Energy CentreEngland and Wales, Storage with solar or windAdded to the registerNew
- FeckenhamEngland and Wales, Storage with solar or windAdded to the registerNew
- Feckenham Greener Grid ParkEngland and Wales, StorageTechnology changed from Storage to Storage, Reactive compensation
- Feckenham Greener Grid ParkEngland and Wales, StorageTechnology changed from Storage, Reactive compensation to Storage
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?