Langage 400kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Langage Battery Storage | LANGAGE ENERGY PARK LIMITED | Storage | 249 | 30 Oct 2031 | Not stated | Scoping |
| Langage 400 | ENSO GREEN HOLDINGS X LIMITED | Storage with solar or wind | 400 | 19 Dec 2036 | Gate 1 | Scoping |
| Langage Farm | Langage 10 Renewables Limited | Storage with solar or wind | 1,000 | 19 Dec 2037 | Gate 1 | Scoping |
| Langage | EP LANGAGE LIMITED | Thermal (gas, biomass, waste) | 0 | Connected | Not stated | Built |
Recent changes
- Langage FarmEngland and Wales, Storage with solar or windMarked as Gate 1
- Langage 400England and Wales, Storage with solar or windStage 1: Marked as Gate 1
- Langage 400England and Wales, Storage with solar or windStage 2: Marked as Gate 1
- Langage 400England and Wales, Storage with solar or windStage 3: Marked as Gate 1
- Langage 400England and Wales, Storage with solar or windCustomer changed from ENSO GREEN HOLDINGS LIMITED to ENSO GREEN HOLDINGS X LIMITED
- Langage FarmEngland and Wales, Storage with solar or windCustomer changed from Hatchworks Investments Ltd to Langage 10 Renewables Limited
- Langage FarmEngland and Wales, Storage with solar or windAdded to the registerNew
- LangageEngland and Wales, Thermal (gas, biomass, waste)Substation name updated in the register (from Langage 400kV to Langage 400kV Substation)
- Langage 400England and Wales, Storage with solar or windAdded to the registerNew
- Langage Battery StorageEngland and Wales, StorageSubstation name updated in the register (from Langage 400kV to Langage 400kV Substation)
- Langage Battery StorageEngland and Wales, StorageAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?