QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.
Projects / Company

RWE GENERATION UK PLC

Customer named in the TEC register

14projects in the register
1.6 GWstill to connect
350 MWof that with Gate 2 offers
7.4 GWconnected now

Projects

ProjectConnection siteTechnologyQueued MWConnection dateGateStatus
Pembroke BESSPembroke 400kV SubstationStorage3507 Mar 2029 +16 moGate 2Consented
STALLINGBOROUGH CARBON CAPTURE CCGTGrimsby West 400kV SubstationThermal (gas, biomass, waste)90630 May 2035Not statedScoping
Didcot BDidcot 400kV SubstationThermal (gas, biomass, waste)23031 Oct 2037Gate 1Built
Sutton CourtenayDidcot 132kV SubstationStorage15031 Oct 2037Not statedScoping
CheshireCapenhurst GSPThermal (gas, biomass, waste)0ConnectedNot statedBuilt
CowesFawley 400kV SubstationThermal (gas, biomass, waste)0ConnectedNot statedBuilt
Cwm DyliTrawsfynydd 275kV SubstationHydro & marine0ConnectedNot statedBuilt
Didcot A GTsDidcot 400kV SubstationThermal (gas, biomass, waste)0ConnectedNot statedBuilt
DolgarrogPentir GSPHydro & marine0ConnectedNot statedBuilt
Great YarmouthNorwich Main 132kVThermal (gas, biomass, waste)0ConnectedNot statedBuilt
Kings Lynn AWalpole 132kV SubstationThermal (gas, biomass, waste)0ConnectedNot statedBuilt
Little BarfordEaton Socon 400kV SubstationThermal (gas, biomass, waste)0ConnectedGate 1Built
Pembroke Power StationPembroke 400kV SubstationOther0ConnectedNot statedBuilt
Staythorpe CStaythorpe 400kV SubstationThermal (gas, biomass, waste)0ConnectedNot statedBuilt

Recent changes

  • Pembroke BESSEngland and Wales, StorageStage 1: Status changed from Awaiting consent to Consented
  • Pembroke BESSEngland and Wales, StorageStage 2: Status changed from Scoping to Consented
  • Pembroke BESSEngland and Wales, StorageRestructured from 1 stage (350 MW from 29 Oct 2027) to 2 stages (285 MW from 7 Mar 2029, 65 MW from 25 May 2029). First connection date +16 months+16 mo
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn't tell you what to do about it. That's what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose