Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / Substation

Didcot 400kV Substation

England and Wales, National Grid Electricity Transmission

4projects in the register
830 MWstill to connect
300 MWof that with Gate 2 offers
1.6 GWconnected now

The queue at this substation

ProjectCustomerTechnologyQueued MWConnection dateGateStatus
Didcot Energy ParkBROCKWELL STORAGE & SOLAR LIMITEDStorage30031 Oct 2027Not statedAwaiting Consents
Didcot RoadDIDCOT BESS LIMITEDStorage30031 Oct 2028 +12 moGate 2Consents Approved
Didcot BRWE Generation UK PlcThermal (gas, biomass, waste)23031 Oct 2037Gate 1Built
Didcot A GTsRWE Generation UK PlcThermal (gas, biomass, waste)0ConnectedNot statedBuilt

Recent changes

  • Didcot RoadEngland and Wales, StorageConnection date moved from 31 Oct 2027 to 31 Oct 2028 (+12 months)+12 mo
  • Didcot RoadEngland and Wales, StorageStatus changed from Scoping to Consents Approved
  • Didcot RoadEngland and Wales, StorageGiven a Gate 2 connection offerGate 2
  • Didcot RoadEngland and Wales, StorageCustomer changed from TBC 001 LIMITED to DIDCOT BESS LIMITED
  • Didcot BEngland and Wales, Thermal (gas, biomass, waste)Marked as Gate 1
  • Didcot BEngland and Wales, Thermal (gas, biomass, waste)Technology changed from Gas (CCGT) to Gas (CCGT), Storage
  • Didcot RoadEngland and Wales, StorageCustomer changed from ARLINGTON ENERGY (DEVELOPMENT) LIMITED to TBC 001 Limited
  • Didcot Energy ParkEngland and Wales, StorageCustomer changed from RNA-ENERGY LTD to BROCKWELL STORAGE & SOLAR LIMITED
  • Didcot BEngland and Wales, Thermal (gas, biomass, waste)Capacity changed from 0 MW to 230 MW
  • Didcot BEngland and Wales, Thermal (gas, biomass, waste)Connection date set to 31 Oct 2037
  • Didcot RoadEngland and Wales, StorageAdded to the registerNew
  • Didcot Energy ParkEngland and Wales, StorageAdded to the registerNew
  • Didcot A GTsEngland and Wales, Thermal (gas, biomass, waste)Substation name updated in the register (from Didcot 400kV to Didcot 400kV Substation)
  • Didcot BEngland and Wales, Thermal (gas, biomass, waste)Substation name updated in the register (from Didcot 400kV to Didcot 400kV Substation)
  • Didcot BEngland and Wales, Thermal (gas, biomass, waste)25 MW now connectedConnected
  • Didcot BEngland and Wales, Thermal (gas, biomass, waste)Capacity changed from 1,450 MW to 1,475 MW
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO