Projects / Substation

Didcot 400kV Substation

England and Wales, National Grid Electricity Transmission

4projects in the register
830 MWstill to connect
0 MWof that with Gate 2 offers
1.6 GWconnected now

The queue at this substation

ProjectCustomerTechnologyQueued MWConnection dateGateStatus
Didcot Energy ParkBROCKWELL STORAGE & SOLAR LIMITEDStorage30031 Oct 2027Not statedAwaiting consent
Didcot RoadTBC 001 LIMITEDStorage30031 Oct 2027Not statedScoping
Didcot BRWE GENERATION UK PLCThermal (gas, biomass, waste)23031 Oct 2037Gate 1Built
Didcot A GTsRWE GENERATION UK PLCThermal (gas, biomass, waste)0ConnectedNot statedBuilt

Recent changes

No changes here since 14 Aug 2026.

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn't tell you what to do about it. That's what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose