Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / Substation

Pembroke 400kV Substation

England and Wales, National Grid Electricity Transmission

7projects in the register
1.5 GWstill to connect
350 MWof that with Gate 2 offers
2.2 GWconnected now

The queue at this substation

ProjectCustomerTechnologyQueued MWConnection dateGateStatus
Llŷr Floating WindLlŷr Floating Wind LimitedOffshore wind20031 Oct 2028Not statedScoping
Pembroke BESS and Solar StationRenesola Hercules Energy 1 LimitedStorage with solar or wind99.931 Oct 2028Not statedAwaiting Consents
Pembroke BESSRWE Generation UK PlcStorage3507 Mar 2029 +16 moGate 2Consents Approved
Llywelyn Floating Offshore Wind FarmRenantis UK LimitedOffshore wind30031 Mar 2029Gate 1Scoping
Valorous Offshore Wind FarmBlue Gem Wind LimitedOffshore wind30031 Oct 2031Not statedScoping
Lambeeth 240MWECODEV GROUP LTDStorage24031 Dec 2037Gate 1Scoping
Pembroke Power StationRWE Generation UK PlcOther0ConnectedNot statedBuilt

Recent changes

  • Lambeeth 240MWEngland and Wales, StorageAdded to the registerNew
  • Lambeeth 240MWEngland and Wales, StorageLeft the register (240 MW from 31 Dec 2037)240 MW
  • Lambeeth 240MWEngland and Wales, StorageMarked as Gate 1
  • Pembroke BESSEngland and Wales, StorageStage 1: Status changed from Awaiting Consents to Consents Approved
  • Pembroke BESSEngland and Wales, StorageStage 2: Status changed from Scoping to Consents Approved
  • Pembroke BESSEngland and Wales, StorageRestructured from 1 stage (350 MW from 29 Oct 2027) to 2 stages (285 MW from 7 Mar 2029, 65 MW from 25 May 2029). First connection date +16 months+16 mo
  • Llywelyn Floating Offshore Wind FarmEngland and Wales, Offshore windMarked as Gate 1
  • Pembroke Power StationEngland and Wales, OtherTechnology changed from Gas (CCGT) to Demand, Hydrogen
  • Llŷr Floating WindEngland and Wales, Offshore windCapacity changed from 1,800 MW to 200 MW
  • Llŷr Floating WindEngland and Wales, Offshore windConnection date moved from 31 Oct 2031 to 31 Oct 2028 (−36 months)−36 mo
  • Llywelyn Floating Offshore Wind FarmEngland and Wales, Offshore windCustomer changed from Nadara Limited to Renantis UK Limited
  • Llywelyn Floating Offshore Wind FarmEngland and Wales, Offshore windCustomer changed from RENANTIS UK LIMITED to Nadara Limited
  • Valorous Offshore Wind FarmEngland and Wales, Offshore windConnection date moved from 2 Apr 2029 to 31 Oct 2031 (+31 months)+31 mo
  • Lambeeth 240MWEngland and Wales, StorageAdded to the registerNew
  • Pembroke BESSEngland and Wales, StorageConnection date moved from 1 Oct 2026 to 29 Oct 2027 (+13 months)+13 mo
  • Llŷr Floating WindEngland and Wales, Offshore windConnection point changed from Alverdiscott 400kV Substation to Pembroke 400kV Substation
  • Llywelyn Floating Offshore Wind FarmEngland and Wales, Offshore windConnection point changed from Alverdiscott 400kV Substation to Pembroke 400kV Substation
  • Pembroke BESSEngland and Wales, StorageConnection point changed from Alverdiscott 400kV Substation to Pembroke 400kV Substation
  • Pembroke BESS and Solar StationEngland and Wales, Storage with solar or windConnection point changed from Alverdiscott 400kV Substation to Pembroke 400kV Substation
  • Pembroke Power StationEngland and Wales, OtherConnection point changed from Alverdiscott 400kV Substation to Pembroke 400kV Substation
  • Valorous Offshore Wind FarmEngland and Wales, Offshore windConnection point changed from Alverdiscott 400kV Substation to Pembroke 400kV Substation
  • Llŷr Floating WindEngland and Wales, Offshore windConnection point changed from Pembroke 400kV Substation to Alverdiscott 400kV Substation
  • Llywelyn Floating Offshore Wind FarmEngland and Wales, Offshore windConnection point changed from Pembroke 400kV Substation to Alverdiscott 400kV Substation
  • Pembroke BESSEngland and Wales, StorageConnection point changed from Pembroke 400kV Substation to Alverdiscott 400kV Substation
  • Pembroke BESS and Solar StationEngland and Wales, Storage with solar or windConnection point changed from Pembroke 400kV Substation to Alverdiscott 400kV Substation
  • Pembroke Power StationEngland and Wales, OtherConnection point changed from Pembroke 400kV Substation to Alverdiscott 400kV Substation
  • Valorous Offshore Wind FarmEngland and Wales, Offshore windConnection point changed from Pembroke 400kV Substation to Alverdiscott 400kV Substation
  • Llŷr Floating WindEngland and Wales, Offshore windSubstation name updated in the register (from Pembroke 400kV to Pembroke 400kV Substation)
  • Llywelyn Floating Offshore Wind FarmEngland and Wales, Offshore windSubstation name updated in the register (from Pembroke 400kV to Pembroke 400kV Substation)
  • Pembroke BESSEngland and Wales, StorageSubstation name updated in the register (from Pembroke 400kV to Pembroke 400kV Substation)
  • Pembroke BESS and Solar StationEngland and Wales, Storage with solar or windSubstation name updated in the register (from Pembroke 400kV to Pembroke 400kV Substation)
  • Pembroke Power StationEngland and Wales, OtherSubstation name updated in the register (from Pembroke 400kV to Pembroke 400kV Substation)
  • Valorous Offshore Wind FarmEngland and Wales, Offshore windSubstation name updated in the register (from Pembroke 400kV to Pembroke 400kV Substation)
  • Llywelyn Floating Offshore Wind FarmEngland and Wales, Offshore windCustomer changed from FALCK RENEWABLES WIND LIMITED to RENANTIS UK LIMITED
  • Pembroke BESSEngland and Wales, StorageRenamed from Milford Haven
  • Pembroke BESSEngland and Wales, StorageCustomer changed from EGNEDOL PEMBROKE ECO-POWER LIMITED to RWE GENERATION UK PLC
  • Pembroke BESSEngland and Wales, StorageTechnology changed from Biomass to Storage
  • Pembroke BESSEngland and Wales, StorageRenamed from Pembroke BESS
  • Pembroke BESSEngland and Wales, StorageTechnology changed from Storage to Biomass
  • Pembroke BESSEngland and Wales, StorageRenamed from Milford Haven
  • Pembroke BESSEngland and Wales, StorageConnection date moved from 31 Oct 2022 to 1 Oct 2026 (+47 months)+47 mo
  • Pembroke BESSEngland and Wales, StorageTechnology changed from Biomass to Storage
  • Pembroke BESS and Solar StationEngland and Wales, Storage with solar or windAdded to the registerNew
  • Llŷr Floating WindEngland and Wales, Offshore windAdded to the registerNew
  • Llywelyn Floating Offshore Wind FarmEngland and Wales, Offshore windAdded to the registerNew
  • Valorous Offshore Wind FarmEngland and Wales, Offshore windConnection date moved from 4 Feb 2029 to 2 Apr 2029 (+2 months)+2 mo
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO