Capenhurst GSP
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Hill Farm | QAIR RENEWABLES UK LIMITED | Storage | 240 | 30 Oct 2037 | Gate 1 | Scoping |
| Mill Hey_Capenhurst BESS | FIRSTWAY SOLAR LTD | Storage | 200 | 30 Oct 2037 | Not stated | Scoping |
| Cheshire | RWE Generation UK Plc | Thermal (gas, biomass, waste) | 0 | Connected | Not stated | Built |
Recent changes
- Hill FarmEngland and Wales, StorageConnection date moved from 30 Oct 2035 to 30 Oct 2037 (+24 months)+24 mo
- Hill FarmEngland and Wales, StorageConnection date moved from 31 Oct 2037 to 30 Oct 2035 (−24 months)−24 mo
- Hill FarmEngland and Wales, StorageMarked as Gate 1
- Mill Hey_Capenhurst BESSEngland and Wales, StorageAdded to the registerNew
- CheshireEngland and Wales, Thermal (gas, biomass, waste)Connection point changed from Capenhurst (Ince) 132kV to Capenhurst GSP
- CheshireEngland and Wales, Thermal (gas, biomass, waste)Technology changed from Gas (OCGT) to Gas engines
- Hill FarmEngland and Wales, StorageCustomer changed from Greenswitch Capital Limited to QAIR RENEWABLES UK LIMITED
- CheshireEngland and Wales, Thermal (gas, biomass, waste)Connection point changed from Capenhurst 275kV Substation to Capenhurst (Ince) 132kV
- Hill FarmEngland and Wales, StorageAdded to the registerNew
- CheshireEngland and Wales, Thermal (gas, biomass, waste)Substation name updated in the register (from Capenhurst 275kV to Capenhurst 275kV Substation)
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?