QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.
Projects / England and Wales
Connection date
7 Mar 2029 +16 months since 14 Aug
Gate
Gate 2
Status
Consented
Technology
Storage
Total capacity
350 MW
Connected now
0 MW
Still to connect
350 MW
Transmission owner
National Grid Electricity Transmission (NGET)
Agreement type
Direct Connection
Region
England and Wales
Project number
PRO-000337
Tracked since
14 Aug 2026

Stages

StageConnected MWAdds MWCumulative MWDateGateStatus
102852857 Mar 2029Gate 2Consented
206535025 May 2029Gate 2Consented

Change history

Every change to this project across 9 registers from 14 Aug 2026 to 21 Sep 2026.

  • 18 Sep 2026 register
    Stage 1: Status changed from Awaiting consent to Consented
  • 18 Sep 2026 register
    Stage 2: Status changed from Scoping to Consented
  • 1 Sep 2026 register
    Restructured from 1 stage (350 MW from 29 Oct 2027) to 2 stages (285 MW from 7 Mar 2029, 65 MW from 25 May 2029). First connection date +16 months