Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

FRV Powertek Limited

Customer named in the TEC register

11projects in the register
3 GWstill to connect
0 MWof that with Gate 2 offers
0 MWconnected now

Projects

ProjectConnection siteTechnologyQueued MWConnection dateGateStatus
TH RenfrewshireTH Renfrwshire 275kV SubstationStorage25031 Oct 2033Gate 1Scoping
TH Stow ManorTrent Valley South Connection Node B 400kV SubstationStorage40030 Oct 2034Not statedAwaiting Consents
TH Stocking PelhamWest Anglia Connection Node E 400kV SubstationStorage40031 Oct 2034Not statedScoping
Tyler Hill Bicker FenCoddington 400kV SubstationStorage40030 May 2035Not statedScoping
TH KnaresboroughLeeds North Connection Node A 400kV SubstationStorage20030 Oct 2036Not statedScoping
TH Bridge FarmImperial Park B 400kV SubstationStorage40031 Oct 2037Gate 1Scoping
TH DidcotChiltern Connection Node D 400kVStorage20031 Oct 2037Gate 1Scoping
TH Maes MelinSouth Wales West Connection Node A 400kV SubstationStorage20031 Oct 2037Not statedScoping
TH NinfieldSussex and Romney Connection Node A 400kV SubstationStorage20031 Oct 2037Gate 1Scoping
TH West WeybridgeLondon West Connection Node B 400kV SubstationStorage20031 Oct 2037Gate 1Scoping
Tyler Hill IverLondon West Connection Node A 400kV SubstationStorage20031 Oct 2038Gate 1Awaiting Consents

Recent changes

  • TH NinfieldEngland and Wales, StorageConnection point changed from Ninfield GSP to Sussex and Romney Connection Node A 400kV Substation
  • TH NinfieldEngland and Wales, StorageMarked as Gate 1
  • TH Bridge FarmEngland and Wales, StorageMarked as Gate 1
  • TH RenfrewshireSouth Scotland, StorageMarked as Gate 1
  • TH DidcotEngland and Wales, StorageMarked as Gate 1
  • TH West WeybridgeEngland and Wales, StorageMarked as Gate 1
  • Tyler Hill IverEngland and Wales, StorageMarked as Gate 1
  • TH Bridge FarmEngland and Wales, StorageCustomer changed from FRV TH Powertek Limited to FRV Powertek Limited
  • TH DidcotEngland and Wales, StorageCustomer changed from FRV TH Powertek Limited to FRV Powertek Limited
  • TH KnaresboroughEngland and Wales, StorageCustomer changed from FRV TH Powertek Limited to FRV Powertek Limited
  • TH Maes MelinEngland and Wales, StorageCustomer changed from FRV TH Powertek Limited to FRV Powertek Limited
  • TH NinfieldEngland and Wales, StorageCustomer changed from FRV TH Powertek Limited to FRV Powertek Limited
  • TH RenfrewshireSouth Scotland, StorageCustomer changed from FRV TH Powertek Limited to FRV Powertek Limited
  • TH Stocking PelhamEngland and Wales, StorageCustomer changed from FRV TH Powertek Limited to FRV Powertek Limited
  • TH Stow ManorEngland and Wales, StorageCustomer changed from FRV TH Powertek Limited to FRV Powertek Limited
  • TH West WeybridgeEngland and Wales, StorageCustomer changed from FRV TH Powertek Limited to FRV Powertek Limited
  • Tyler Hill Bicker FenEngland and Wales, StorageCustomer changed from FRV TH Powertek Limited to FRV Powertek Limited
  • Tyler Hill Bicker FenEngland and Wales, StorageConnection point changed from Bicker Fen 400kV Substation to Coddington 400kV Substation
  • Tyler Hill IverEngland and Wales, StorageCustomer changed from FRV TH Powertek Limited to FRV Powertek Limited
  • TH DidcotEngland and Wales, StorageConnection point changed from Chiltern Connection Node A 400kV to Chiltern Connection Node D 400kV
  • TH Bridge FarmEngland and Wales, StorageConnection point changed from Imperial Park 400kV Substation to Imperial Park B 400kV Substation
  • TH DidcotEngland and Wales, StorageConnection point changed from Didcot 400kV Substation to Chiltern Connection Node A 400kV
  • TH KnaresboroughEngland and Wales, StorageConnection point changed from Knaresborough 275kV Substation to Leeds North Connection Node A 400kV Substation
  • TH KnaresboroughEngland and Wales, StorageConnection date moved from 31 Oct 2036 to 30 Oct 2036 (1 day earlier)
  • TH Maes MelinEngland and Wales, StorageConnection point changed from Swansea North 275kV Substation to South Wales West Connection Node A 400kV Substation
  • TH NinfieldEngland and Wales, StorageAdded to the registerNew
  • TH RenfrewshireSouth Scotland, StorageAdded to the registerNew
  • TH Stocking PelhamEngland and Wales, StorageConnection point changed from Pelham 400kV Substation to West Anglia Connection Node E 400kV Substation
  • TH Stocking PelhamEngland and Wales, StorageConnection date moved from 31 Oct 2032 to 31 Oct 2034 (+24 months)+24 mo
  • TH Stow ManorEngland and Wales, StorageConnection point changed from Cottam 400kV Substation to Trent Valley South Connection Node B 400kV Substation.
  • TH Stow ManorEngland and Wales, StorageConnection date moved from 31 Oct 2033 to 30 Oct 2034 (+12 months)+12 mo
  • Tyler Hill IverEngland and Wales, StorageConnection point changed from Iver 275kV Substation to London West Connection Node A 400kV Substation
  • Tyler Hill IverEngland and Wales, StorageConnection date moved from 31 Oct 2037 to 31 Oct 2038 (+12 months)+12 mo
  • TH West WeybridgeEngland and Wales, StorageConnection point changed from West Weybridge 400kV Substation to London West Connection Node B 400kV Substation
  • TH Bridge FarmEngland and Wales, StorageAdded to the registerNew
  • TH DidcotEngland and Wales, StorageAdded to the registerNew
  • TH Maes MelinEngland and Wales, StorageAdded to the registerNew
  • TH Stocking PelhamEngland and Wales, StorageAdded to the registerNew
  • TH West WeybridgeEngland and Wales, StorageAdded to the registerNew
  • TH KnaresboroughEngland and Wales, StorageAdded to the registerNew
  • Tyler Hill Bicker FenEngland and Wales, StorageAdded to the registerNew
  • TH Stow ManorEngland and Wales, StorageAdded to the registerNew
  • Tyler Hill IverEngland and Wales, StorageAdded to the registerNew
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO