Tyler Hill Iver
FRV Powertek Limited at London West Connection Node A 400kV Substation
- Connection date
- 31 Oct 2038
- Gate
- Gate 1
- Status
- Awaiting Consents
- Technology
- Storage
- Total capacity
- 200 MW
- Connected now
- 0 MW
- Still to connect
- 200 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-004134
- In the register since
- September 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 19 Dec 2025 registerMarked as Gate 1
- 29 Jul 2025 registerCustomer changed from FRV TH Powertek Limited to FRV Powertek Limited
- 27 Sep 2024 registerConnection point changed from Iver 275kV Substation to London West Connection Node A 400kV Substation
- 27 Sep 2024 registerConnection date moved from 31 Oct 2037 to 31 Oct 2038 (+12 months)
- 29 Sep 2023 registerAdded to the register
Also at London West Connection Node A 400kV Substation
Substation viewNo other projects in the register at this connection point.