TH Stocking Pelham
FRV Powertek Limited at West Anglia Connection Node E 400kV Substation
- Connection date
- 31 Oct 2034
- Gate
- Not stated
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 400 MW
- Connected now
- 0 MW
- Still to connect
- 400 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-002791
- In the register since
- January 2024
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 29 Jul 2025 registerCustomer changed from FRV TH Powertek Limited to FRV Powertek Limited
- 27 Sep 2024 registerConnection point changed from Pelham 400kV Substation to West Anglia Connection Node E 400kV Substation
- 27 Sep 2024 registerConnection date moved from 31 Oct 2032 to 31 Oct 2034 (+24 months)
- 30 Jan 2024 registerAdded to the register
Also at West Anglia Connection Node E 400kV Substation
Substation view1 other project, 800 MW still to connect at this substation in total.