Imperial Park B 400kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| IPC Grid Tremorfa | IPC GRID CONNECTION LIMITED | Storage | 1,000 | 6 Dec 2036 | Gate 1 | Scoping |
| TH Bridge Farm | FRV Powertek Limited | Storage | 400 | 31 Oct 2037 | Gate 1 | Scoping |
Recent changes
- IPC Grid TremorfaEngland and Wales, StorageMarked as Gate 1
- TH Bridge FarmEngland and Wales, StorageMarked as Gate 1
- TH Bridge FarmEngland and Wales, StorageCustomer changed from FRV TH Powertek Limited to FRV Powertek Limited
- IPC Grid TremorfaEngland and Wales, StorageConnection point changed from Imperial Park 400kV Substation to Imperial Park B 400kV Substation
- IPC Grid TremorfaEngland and Wales, StorageCapacity changed from 500 MW to 1,000 MW
- IPC Grid TremorfaEngland and Wales, StorageConnection date moved from 31 Oct 2037 to 6 Dec 2036 (−11 months)−11 mo
- TH Bridge FarmEngland and Wales, StorageConnection point changed from Imperial Park 400kV Substation to Imperial Park B 400kV Substation
- IPC Grid TremorfaEngland and Wales, StorageConnection point changed from Tremorfa 275kV Substation to Imperial Park 400kV Substation
- TH Bridge FarmEngland and Wales, StorageAdded to the registerNew
- IPC Grid TremorfaEngland and Wales, StorageAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?