IB VOGT UK LTD
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Lackenby PV & BESS Station | Teeside Connection Node A 400kV Substation | Storage with solar or wind | 240 | 31 Oct 2033 | Gate 1 | Scoping |
| St Fergus | St Fergus | Storage with solar or wind | 100 | 31 Oct 2033 | Gate 1 | Scoping |
| Bicker Fen | Trent Valley South Connection Node C 400kV Substation | Storage with solar or wind | 400 | 30 Oct 2034 | Gate 1 | Scoping |
| Morton Manor PV & BESS Station | High Marnham 400kV Substation | Storage with solar or wind | 240 | 30 Oct 2034 −36 mo | Gate 1 | Scoping |
| Butlers Wood PV & BESS Station | South Anglia Connection Node B 400kV Substation | Storage with solar or wind | 240 | 31 Oct 2034 | Gate 1 | Scoping |
| Cellarhead PV & BESS Station | Manchester South Connection Node B 400kV Substation | Storage with solar or wind | 400 | 30 Oct 2037 | Not stated | Scoping |
| Feckenham PV & BESS Station | Feckenham 400kV Substation | Storage with solar or wind | 400 | 30 Oct 2037 +48 mo | Gate 1 | Scoping |
Left the register since January 2021: East Quantoxhead PV & BESS Station (240 MW).
Recent changes
- Bicker FenEngland and Wales, Storage with solar or windConnection date moved from 31 Oct 2034 to 30 Oct 2034 (1 day earlier)
- Feckenham PV & BESS StationEngland and Wales, Storage with solar or windConnection date moved from 31 Oct 2033 to 30 Oct 2037 (+48 months)+48 mo
- Morton Manor PV & BESS StationEngland and Wales, Storage with solar or windConnection date moved from 31 Oct 2037 to 30 Oct 2034 (−36 months)−36 mo
- Morton Manor PV & BESS StationEngland and Wales, Storage with solar or windMarked as Gate 1
- Bicker FenEngland and Wales, Storage with solar or windMarked as Gate 1
- St FergusNorth Scotland, Storage with solar or windMarked as Gate 1
- Lackenby PV & BESS StationEngland and Wales, Storage with solar or windConnection point changed from Lackenby 275kV Substation to Teeside Connection Node A 400kV Substation
- Lackenby PV & BESS StationEngland and Wales, Storage with solar or windMarked as Gate 1
- Butlers Wood PV & BESS StationEngland and Wales, Storage with solar or windMarked as Gate 1
- Feckenham PV & BESS StationEngland and Wales, Storage with solar or windMarked as Gate 1
- Bicker FenEngland and Wales, Storage with solar or windAdded to the registerNew
- Butlers Wood PV & BESS StationEngland and Wales, Storage with solar or windConnection date moved from 30 Oct 2034 to 31 Oct 2034 (1 day later)
- Cellarhead PV & BESS StationEngland and Wales, Storage with solar or windConnection date moved from 31 Oct 2037 to 30 Oct 2037 (1 day earlier)
- East Quantoxhead PV & BESS StationEngland and Wales, Storage with solar or windLeft the register (240 MW from 31 Oct 2037)240 MW
- Butlers Wood PV & BESS StationEngland and Wales, Storage with solar or windAdded to the registerNew
- Cellarhead PV & BESS StationEngland and Wales, Storage with solar or windConnection point changed from Cellarhead 400kV Substation to Manchester South Connection Node B 400kV Substation
- St FergusNorth Scotland, Storage with solar or windAdded to the registerNew
- East Quantoxhead PV & BESS StationEngland and Wales, Storage with solar or windConnection point changed from Hinkley Point 400kV Substation to West Country Connection Node D 400kV Substation
- Feckenham PV & BESS StationEngland and Wales, Storage with solar or windAdded to the registerNew
- Lackenby PV & BESS StationEngland and Wales, Storage with solar or windAdded to the registerNew
- Morton Manor PV & BESS StationEngland and Wales, Storage with solar or windAdded to the registerNew
- East Quantoxhead PV & BESS StationEngland and Wales, Storage with solar or windAdded to the registerNew
- Cellarhead PV & BESS StationEngland and Wales, Storage with solar or windAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?