Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / England and Wales

Feckenham Greener Grid Park

Statkraft UK Ltd at Feckenham 400kV Substation

Connection date
31 Oct 2028
Gate
Gate 1
Status
Scoping
Technology
Storage
Total capacity
150 MW
Connected now
0 MW
Still to connect
150 MW
Transmission owner
National Grid Electricity Transmission (NGET)
Agreement type
Direct Connection
Region
England and Wales
Project number
PRO-001008
In the register since
January 2021 or earlier

What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?

Stages

StageConnected MWAdds MWCumulative MWDateGateStatus
10121231 Oct 2028Gate 1Scoping
2013815031 Oct 2032Gate 1Scoping

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 9 Dec 2025 register
    Stage 1: Marked as Gate 1
  • 9 Dec 2025 register
    Stage 2: Marked as Gate 1
  • 29 Apr 2025 register
    Stage 1: Connection date moved from 31 Jan 2026 to 31 Oct 2028 (+33 months)
  • 28 Feb 2025 register
    Stage 1: Technology changed from Storage, Reactive compensation to Storage
  • 28 Feb 2025 register
    Stage 2: Technology changed from Storage, Reactive compensation to Storage
  • 30 Jan 2024 register
    Stage 1: Connection date moved from 27 Oct 2023 to 31 Jan 2026 (+27 months)
  • 29 Dec 2023 register
    Renamed from Feckenham
  • 23 Dec 2022 register
    Restructured from 1 stage (12 MW from 30 Jun 2022) to 2 stages (12 MW from 27 Oct 2023, 138 MW from 31 Oct 2032). First connection date +16 months
  • 29 Jul 2022 register
    Substation name updated in the register (from Feckenham 400kV to Feckenham 400kV Substation)
  • 30 Nov 2021 register
    Technology changed from Storage to Storage, Reactive compensation
  • 30 Apr 2021 register
    Technology changed from Storage, Reactive compensation to Storage

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO