Statkraft UK Ltd
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Lovedean Greener Grid Park | Lovedean 400kV Substation | Storage | 49.9 | 1 Jun 2028 | Gate 1 | Scoping |
| Feckenham Greener Grid Park | Feckenham 400kV Substation | Storage | 150 | 31 Oct 2028 | Gate 1 | Scoping |
| Neilston 400kV Greener Grid Park | Neilston 400kV Substation | Storage | 600 | 31 Oct 2029 +29 mo | Gate 2 | Consents Approved |
| Baillie Greener Grid Park | Baillie 275KV Substation | Storage | 48 | 30 Sep 2030 | Gate 1 | Scoping |
| Statkraft SEWF | Orrin GSP | Onshore wind | 101 | 31 Oct 2033 | Gate 1 | Scoping |
| Cruach Bhreac Wind Farm | Craig Murrail 275kV Substation | Onshore wind | 101 | 31 Oct 2034 | Gate 1 | Scoping |
| East Lincolnshire Solar | Lincolnshire Coastal Node B 400kV Substation | Storage with solar or wind | 800 | 30 May 2035 | Gate 1 | Scoping |
Left the register since January 2021: Bramford Greener Grid Park (0 MW).
Recent changes
- Neilston 400kV Greener Grid ParkSouth Scotland, StorageStatus changed from Awaiting Consents to Consents Approved
- Neilston 400kV Greener Grid ParkSouth Scotland, StorageConnection date moved from 17 May 2027 to 31 Oct 2029 (+29 months)+29 mo
- Neilston 400kV Greener Grid ParkSouth Scotland, StorageGiven a Gate 2 connection offerGate 2
- Baillie Greener Grid ParkNorth Scotland, StorageMarked as Gate 1
- Cruach Bhreac Wind FarmNorth Scotland, Onshore windConnection point changed from Craig Murrail GSP to Craig Murrail 275kV Substation
- Cruach Bhreac Wind FarmNorth Scotland, Onshore windMarked as Gate 1
- East Lincolnshire SolarEngland and Wales, Storage with solar or windMarked as Gate 1
- Feckenham Greener Grid ParkEngland and Wales, StorageStage 1: Marked as Gate 1
- Feckenham Greener Grid ParkEngland and Wales, StorageStage 2: Marked as Gate 1
- Lovedean Greener Grid ParkEngland and Wales, StorageMarked as Gate 1
- Statkraft SEWFNorth Scotland, Onshore windMarked as Gate 1
- Neilston 400kV Greener Grid ParkSouth Scotland, StorageStatus changed from Scoping to Awaiting Consents
- Neilston 400kV Greener Grid ParkSouth Scotland, StorageTechnology changed from Storage, Reactive compensation to Storage
- Feckenham Greener Grid ParkEngland and Wales, StorageStage 1: Connection date moved from 31 Jan 2026 to 31 Oct 2028 (+33 months)+33 mo
- Feckenham Greener Grid ParkEngland and Wales, StorageStage 1: Technology changed from Storage, Reactive compensation to Storage
- Feckenham Greener Grid ParkEngland and Wales, StorageStage 2: Technology changed from Storage, Reactive compensation to Storage
- Statkraft SEWFNorth Scotland, Onshore windConnection point changed from Corriemoillie 2 400/132kV Substation to Orrin GSP
- Statkraft SEWFNorth Scotland, Onshore windAdded to the registerNew
- East Lincolnshire SolarEngland and Wales, Storage with solar or windAdded to the registerNew
- Cruach Bhreac Wind FarmNorth Scotland, Onshore windConnection point changed from Dunoon GSP to Craig Murrail GSP
- Baillie Greener Grid ParkNorth Scotland, StorageConnection date moved from 31 Oct 2026 to 30 Sep 2030 (+47 months)+47 mo
- Cruach Bhreac Wind FarmNorth Scotland, Onshore windAdded to the registerNew
- Bramford Greener Grid ParkEngland and Wales, OtherLeft the register (0 MW from 31 Oct 2029)0 MW
- Feckenham Greener Grid ParkEngland and Wales, StorageStage 1: Connection date moved from 27 Oct 2023 to 31 Jan 2026 (+27 months)+27 mo
- Feckenham Greener Grid ParkEngland and Wales, StorageRenamed from Feckenham
- Neilston 400kV Greener Grid ParkSouth Scotland, StorageCapacity changed from 33 MW to 600 MW
- Lovedean Greener Grid ParkEngland and Wales, StorageRestructured from 2 stages (0 MW from 1 Jun 2024, 49.9 MW from 1 Jun 2026) to 1 stage (49.9 MW from 1 Jun 2028). First connection date +24 months+24 mo
- Neilston 400kV Greener Grid ParkSouth Scotland, StorageConnection date moved from 31 Oct 2026 to 17 May 2027 (+7 months)+7 mo
- Baillie Greener Grid ParkNorth Scotland, StorageSubstation name updated in the register (from Baillie 275KV to Baillie 275KV Substation)
- Feckenham Greener Grid ParkEngland and Wales, StorageRestructured from 1 stage (12 MW from 30 Jun 2022) to 2 stages (12 MW from 27 Oct 2023, 138 MW from 31 Oct 2032). First connection date +16 months+16 mo
- Lovedean Greener Grid ParkEngland and Wales, StorageSubstation name updated in the register (from Lovedean 400kV to Lovedean 400kV Substation)
- Neilston 400kV Greener Grid ParkSouth Scotland, StorageSubstation name updated in the register (from Neilston 400kV to Neilston 400kV Substation)
- Lovedean Greener Grid ParkEngland and Wales, StorageAdded to the registerNew
- Bramford Greener Grid ParkEngland and Wales, OtherAdded to the registerNew
- Feckenham Greener Grid ParkEngland and Wales, StorageSubstation name updated in the register (from Feckenham 400kV to Feckenham 400kV Substation)
- Neilston 400kV Greener Grid ParkSouth Scotland, StorageAdded to the registerNew
- Baillie Greener Grid ParkNorth Scotland, StorageAdded to the registerNew
- Feckenham Greener Grid ParkEngland and Wales, StorageTechnology changed from Storage to Storage, Reactive compensation
- Feckenham Greener Grid ParkEngland and Wales, StorageTechnology changed from Storage, Reactive compensation to Storage
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?