- Connection date
- 31 Oct 2032
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage + Solar
- Total capacity
- 400 MW
- Connected now
- 0 MW
- Still to connect
- 400 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-002086
- In the register since
- June 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 9 Dec 2025 registerMarked as Gate 1
- 24 Dec 2024 registerConnection date moved from 31 Oct 2030 to 31 Oct 2032 (+24 months)
- 24 Dec 2024 registerTechnology changed from Storage, Solar, Onshore wind to Storage, Solar
- 30 Jun 2023 registerAdded to the register
Also at Swansea North 400kV Substation
Substation view7 other projects, 2 GW still to connect at this substation in total. 977 MW is due to connect here before this project’s connection date of 31 Oct 2032.
- Swansea Greener Grid Park - Connection 1SWANSEA GRID SOLUTIONS LIMITED, Storage, Not statedAug 202497 MW
- Swansea Greener Grid Park - Connection 2SWANSEA GRID SOLUTIONS LIMITED, Other, Not statedJul 20250 MW
- Swansea NorthEDF ENERGY RENEWABLES LIMITED, Storage, Gate 1Jul 202849.9 MW
- Swansea North Green Energy CentreSWANSEA NORTH GREEN NG LIMITED, Storage with solar or wind, Not statedOct 20281 GW
- BESS SwanREWE 3 LIMITED, Storage, Not statedOct 2028200 MW
- Hirfynydd and Mynydd DrumaurEDF ENERGY RENEWABLES LIMITED, Storage with solar or wind, Gate 1Oct 2030249 MW
- Peak Gen LlandarcyPEAK GEN POWER 5 LIMITED, Thermal (gas, biomass, waste), Not statedConnected21 MW