QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.
Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / England and Wales

Swansea Greener Grid Park - Connection 1

SWANSEA GRID SOLUTIONS LIMITED at Swansea North 400kV Substation

Connection date
31 Aug 2024
Gate
Not stated
Status
Under Construction/Commissioning
Planning consent
Granted 9 Aug 2021
Swansea, reference 2021/0163/FUL · Source: REPD
Technology
Storage + Reactive compensation
Total capacity
97 MW
Connected now
0 MW
Still to connect
97 MW
Transmission owner
National Grid Electricity Transmission (NGET)
Agreement type
Direct Connection
Region
England and Wales
Project number
PRO-001120
In the register since
January 2021 or earlier

What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?

Stages

StageConnected MWAdds MWCumulative MWDateGateStatus
10121231 Aug 2024Not statedUnder Construction/Commissioning
20859731 Oct 2028Not statedScoping

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 21 Nov 2025 register
    Stage 1: Status changed from Consents Approved to Under Construction/Commissioning
  • 31 Oct 2023 register
    Customer changed from STATKRAFT UK LTD to Swansea Grid Solutions Limited
  • 30 May 2023 register
    Renamed from Swansea North
  • 23 Dec 2022 register
    Substation name updated in the register (from Swansea North 400kV to Swansea North 400kV Substation)
  • 29 Nov 2022 register
    Restructured from 1 stage (12 MW from 30 Oct 2027) to 2 stages (12 MW from 31 Aug 2024, 85 MW from 31 Oct 2028). First connection date −38 months
  • 30 Nov 2021 register
    Technology changed from Storage to Storage, Reactive compensation
  • 30 Apr 2021 register
    Technology changed from Storage, Reactive compensation to Storage

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO

Planning consent

The planning decision or stage for this project, from DESNZ’s Renewable Energy Planning Database (REPD), July 2026 edition, with the planning authority and its reference. QueueWatch matched the project to that record. NESO’s status can lag behind planning decisions, so the two may differ.

How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.