Llywelyn Floating Offshore Wind Farm
- Connection date
- 31 Mar 2029
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Offshore wind
- Total capacity
- 300 MW
- Connected now
- 0 MW
- Still to connect
- 300 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001668
- In the register since
- December 2021
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 27 Mar 2026 registerMarked as Gate 1
- 28 Mar 2025 registerCustomer changed from Nadara Limited to Renantis UK Limited
- 28 Feb 2025 registerCustomer changed from RENANTIS UK LIMITED to Nadara Limited
- 30 Jun 2023 registerConnection point changed from Alverdiscott 400kV Substation to Pembroke 400kV Substation
- 30 May 2023 registerConnection point changed from Pembroke 400kV Substation to Alverdiscott 400kV Substation
- 28 Apr 2023 registerSubstation name updated in the register (from Pembroke 400kV to Pembroke 400kV Substation)
- 31 Jan 2023 registerCustomer changed from FALCK RENEWABLES WIND LIMITED to RENANTIS UK LIMITED
- 31 Dec 2021 registerAdded to the register
Also at Pembroke 400kV Substation
Substation view6 other projects, 1.5 GW still to connect at this substation in total. 585 MW is due to connect here before this project’s connection date of 31 Mar 2029.
- Llŷr Floating WindLlŷr Floating Wind Limited, Offshore wind, Not statedOct 2028200 MW
- Pembroke BESS and Solar StationRenesola Hercules Energy 1 Limited, Storage with solar or wind, Not statedOct 202899.9 MW
- Pembroke BESSRWE Generation UK Plc, Storage, Gate 2Mar 2029350 MW
- Valorous Offshore Wind FarmBlue Gem Wind Limited, Offshore wind, Not statedOct 2031300 MW
- Lambeeth 240MWECODEV GROUP LTD, Storage, Gate 1Dec 2037240 MW
- Pembroke Power StationRWE Generation UK Plc, Other, Not statedConnected2.2 GW