Renantis UK Limited
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Llywelyn Floating Offshore Wind Farm | Pembroke 400kV Substation | Offshore wind | 300 | 31 Mar 2029 | Gate 1 | Scoping |
| Gleann Eoghainn | Dunvegan 132/33kV Grid Supply Point Substation | Onshore wind | 25 | 30 Nov 2029 | Not stated | Scoping |
| Assel Valley Extension Wind Farm | Maybole GSP | Storage with solar or wind | 175 | 31 Oct 2032 | Gate 1 | Scoping |
| Millennium East | FORT AUGUSTUS 2 400/33kV GRID SUPPLY POINT SUBSTATION | Onshore wind | 49.9 | 31 Oct 2035 | Gate 1 | Scoping |
| Peninsula Energy Park | PENINSULA ENERGY PARK 220kV SUBSTATION | Onshore wind | 250 | 31 Oct 2035 | Gate 1 | Scoping |
| Llywelyn Extension Offshore Wind Farm | LLYWELYN EXTENSION OFFSHORE WIND FARM 66/275KV OFFSHORE SUBSTATION | Offshore wind | 1,000 | 6 Dec 2036 | Gate 1 | Scoping |
Left the register since January 2021: Millennium South (25 MW), Longhaven Offshore Wind Farm (100 MW).
Recent changes
- Llywelyn Extension Offshore Wind FarmEngland and Wales, Offshore windMarked as Gate 1
- Millennium EastNorth Scotland, Onshore windConnection point changed from Fort Augustus GSP/New Fort Augustus GSP to FORT AUGUSTUS 2 400/33kV GRID SUPPLY POINT SUBSTATION
- Millennium EastNorth Scotland, Onshore windMarked as Gate 1
- Peninsula Energy ParkNorth Scotland, Onshore windConnection point changed from Taynuilt GSP to PENINSULA ENERGY PARK 220kV SUBSTATION
- Peninsula Energy ParkNorth Scotland, Onshore windMarked as Gate 1
- Llywelyn Extension Offshore Wind FarmEngland and Wales, Offshore windConnection point changed from Pembroke 400kV Substation to LLYWELYN EXTENSION OFFSHORE WIND FARM 66/275KV OFFSHORE SUBSTATION
- Llywelyn Floating Offshore Wind FarmEngland and Wales, Offshore windMarked as Gate 1
- Assel Valley Extension Wind FarmSouth Scotland, Storage with solar or windStage 1: Marked as Gate 1
- Assel Valley Extension Wind FarmSouth Scotland, Storage with solar or windStage 2: Marked as Gate 1
- Gleann EoghainnNorth Scotland, Onshore windConnection point changed from Edinbane 132/33kV Substation to Dunvegan 132/33kV Grid Supply Point Substation
- Gleann EoghainnNorth Scotland, Onshore windConnection point changed from Dunvegan GSP to Edinbane 132/33kV Substation
- Gleann EoghainnNorth Scotland, Onshore windConnection date moved from 31 Oct 2027 to 30 Nov 2029 (+25 months)+25 mo
- Assel Valley Extension Wind FarmSouth Scotland, Storage with solar or windCustomer changed from Nadara Limited to Renantis UK Limited
- Gleann EoghainnNorth Scotland, Onshore windCustomer changed from Nadara Limited to Renantis UK Limited
- Gleann EoghainnNorth Scotland, Onshore windConnection point changed from Edinbane 132/33kV Substation to Dunvegan GSP
- Llywelyn Extension Offshore Wind FarmEngland and Wales, Offshore windCustomer changed from Nadara Limited to Renantis UK Limited
- Llywelyn Floating Offshore Wind FarmEngland and Wales, Offshore windCustomer changed from Nadara Limited to Renantis UK Limited
- Millennium EastNorth Scotland, Onshore windCustomer changed from Nadara Limited to Renantis UK Limited
- Peninsula Energy ParkNorth Scotland, Onshore windCustomer changed from Nadara Limited to Renantis UK Limited
- Assel Valley Extension Wind FarmSouth Scotland, Storage with solar or windCustomer changed from RENANTIS UK LIMITED to Nadara Limited
- Gleann EoghainnNorth Scotland, Onshore windCustomer changed from RENANTIS UK LIMITED to Nadara Limited
- Llywelyn Extension Offshore Wind FarmEngland and Wales, Offshore windCustomer changed from RENANTIS UK LIMITED to Nadara Limited
- Llywelyn Floating Offshore Wind FarmEngland and Wales, Offshore windCustomer changed from RENANTIS UK LIMITED to Nadara Limited
- Millennium EastNorth Scotland, Onshore windCustomer changed from RENANTIS UK LIMITED to Nadara Limited
- Peninsula Energy ParkNorth Scotland, Onshore windCustomer changed from RENANTIS UK LIMITED to Nadara Limited
- Millennium EastNorth Scotland, Onshore windAdded to the registerNew
- Peninsula Energy ParkNorth Scotland, Onshore windAdded to the registerNew
- Assel Valley Extension Wind FarmSouth Scotland, Storage with solar or windStage 1: Connection date moved from 30 Oct 2032 to 31 Oct 2032 (1 day later)
- Assel Valley Extension Wind FarmSouth Scotland, Storage with solar or windRestructured from 1 stage (88 MW from 30 Oct 2030) to 2 stages (88 MW from 30 Oct 2032, 87 MW from 30 Oct 2037). First connection date +24 months+24 mo
- Longhaven Offshore Wind FarmNorth Scotland, Offshore windLeft the register (100 MW from 31 Oct 2033)100 MW
- Gleann EoghainnNorth Scotland, Onshore windConnection point changed from Dunvegan GSP to Edinbane 132/33kV Substation
- Assel Valley Extension Wind FarmSouth Scotland, Storage with solar or windAdded to the registerNew
- Millennium SouthNorth Scotland, Onshore windLeft the register (25 MW from 31 Oct 2021)25 MW
- Llywelyn Extension Offshore Wind FarmEngland and Wales, Offshore windConnection point changed from Alverdiscott 400kV Substation to Pembroke 400kV Substation
- Llywelyn Floating Offshore Wind FarmEngland and Wales, Offshore windConnection point changed from Alverdiscott 400kV Substation to Pembroke 400kV Substation
- Llywelyn Extension Offshore Wind FarmEngland and Wales, Offshore windConnection point changed from Pembroke 400kV Substation to Alverdiscott 400kV Substation
- Llywelyn Floating Offshore Wind FarmEngland and Wales, Offshore windConnection point changed from Pembroke 400kV Substation to Alverdiscott 400kV Substation
- Llywelyn Extension Offshore Wind FarmEngland and Wales, Offshore windSubstation name updated in the register (from Pembroke 400kV to Pembroke 400kV Substation)
- Llywelyn Floating Offshore Wind FarmEngland and Wales, Offshore windSubstation name updated in the register (from Pembroke 400kV to Pembroke 400kV Substation)
- Gleann EoghainnNorth Scotland, Onshore windAdded to the registerNew
- Llywelyn Extension Offshore Wind FarmEngland and Wales, Offshore windCustomer changed from FALCK RENEWABLES WIND LIMITED to RENANTIS UK LIMITED
- Llywelyn Floating Offshore Wind FarmEngland and Wales, Offshore windCustomer changed from FALCK RENEWABLES WIND LIMITED to RENANTIS UK LIMITED
- Millennium SouthNorth Scotland, Onshore windCustomer changed from FALCK RENEWABLES WIND LIMITED to RENANTIS UK LIMITED
- Longhaven Offshore Wind FarmNorth Scotland, Offshore windCustomer changed from FALCK RENEWABLES WIND LIMITED to RENANTIS UK LIMITED
- Llywelyn Extension Offshore Wind FarmEngland and Wales, Offshore windAdded to the registerNew
- Longhaven Offshore Wind FarmNorth Scotland, Offshore windAdded to the registerNew
- Llywelyn Floating Offshore Wind FarmEngland and Wales, Offshore windAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose