QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.
Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / England and Wales

Valorous Offshore Wind Farm

Blue Gem Wind Limited at Pembroke 400kV Substation

Connection date
31 Oct 2031
Gate
Not stated
Status
Scoping
Technology
Offshore wind
Total capacity
300 MW
Connected now
0 MW
Still to connect
300 MW
Transmission owner
National Grid Electricity Transmission (NGET)
Agreement type
Direct Connection
Region
England and Wales
Project number
PRO-001383
In the register since
January 2021 or earlier

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 24 Dec 2024 register
    Connection date moved from 2 Apr 2029 to 31 Oct 2031 (+31 months)
  • 30 Jun 2023 register
    Connection point changed from Alverdiscott 400kV Substation to Pembroke 400kV Substation
  • 30 May 2023 register
    Connection point changed from Pembroke 400kV Substation to Alverdiscott 400kV Substation
  • 28 Apr 2023 register
    Substation name updated in the register (from Pembroke 400kV to Pembroke 400kV Substation)
  • 26 Feb 2021 register
    Connection date moved from 4 Feb 2029 to 2 Apr 2029 (+2 months)

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO