Blue Gem Wind Limited
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Erebus | Pembroke 132kV Substation | Offshore wind | 95.3 | 26 Jul 2028 | Not stated | Scoping |
| Valorous Offshore Wind Farm | Pembroke 400kV Substation | Offshore wind | 300 | 31 Oct 2031 | Not stated | Scoping |
Recent changes
- Valorous Offshore Wind FarmEngland and Wales, Offshore windConnection date moved from 2 Apr 2029 to 31 Oct 2031 (+31 months)+31 mo
- ErebusEngland and Wales, Offshore windCapacity changed from 91 MW to 95.3 MW
- ErebusEngland and Wales, Offshore windConnection date moved from 2 Nov 2026 to 26 Jul 2028 (+21 months)+21 mo
- Valorous Offshore Wind FarmEngland and Wales, Offshore windConnection point changed from Alverdiscott 400kV Substation to Pembroke 400kV Substation
- Valorous Offshore Wind FarmEngland and Wales, Offshore windConnection point changed from Pembroke 400kV Substation to Alverdiscott 400kV Substation
- Valorous Offshore Wind FarmEngland and Wales, Offshore windSubstation name updated in the register (from Pembroke 400kV to Pembroke 400kV Substation)
- ErebusEngland and Wales, Offshore windSubstation name updated in the register (from Pembroke 132kV to Pembroke 132kV Substation)
- ErebusEngland and Wales, Offshore windConnection date moved from 11 Feb 2026 to 2 Nov 2026 (+9 months)+9 mo
- Valorous Offshore Wind FarmEngland and Wales, Offshore windConnection date moved from 4 Feb 2029 to 2 Apr 2029 (+2 months)+2 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?