Fleet 400kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Fleet EGH (Tertiary) | FLEET GREEN LIMITED | Storage with solar or wind | 47.5 | 13 Jan 2027 | Not stated | Consents Approved |
| Fleet Solar PV | FLEET SOLAR LIMITED | Solar | 57 | 7 Aug 2028 | Not stated | Awaiting Consents |
| Fleet Tertiary | FLEET SOLAR LIMITED | Thermal (gas, biomass, waste) | 47.5 | 7 Aug 2028 +32 mo | Gate 1 | Scoping |
| Fleet (Tertiary) | CSE23 LIMITED | Solar | 47.5 | 30 Jul 2029 +33 mo | Gate 2 | Consents Approved |
Recent changes
- Fleet (Tertiary)England and Wales, SolarGiven a Gate 2 connection offerGate 2
- Fleet TertiaryEngland and Wales, Thermal (gas, biomass, waste)Marked as Gate 1
- Fleet (Tertiary)England and Wales, SolarConnection date moved from 31 Oct 2026 to 30 Jul 2029 (+33 months)+33 mo
- Fleet TertiaryEngland and Wales, Thermal (gas, biomass, waste)Connection date moved from 30 Nov 2025 to 7 Aug 2028 (+32 months)+32 mo
- Fleet Solar PVEngland and Wales, SolarConnection date moved from 13 Dec 2026 to 7 Aug 2028 (+20 months)+20 mo
- Fleet (Tertiary)England and Wales, SolarStatus changed from Scoping to Consents Approved
- Fleet (Tertiary)England and Wales, SolarConnection date moved from 31 Oct 2025 to 31 Oct 2026 (+12 months)+12 mo
- Fleet Solar PVEngland and Wales, SolarTechnology changed from Storage, Solar to Solar
- Fleet EGH (Tertiary)England and Wales, Storage with solar or windStage 1: Capacity changed from 49.9 MW to 47.5 MW
- Fleet EGH (Tertiary)England and Wales, Storage with solar or windStage 1: Connection date moved from 31 Oct 2025 to 13 Jan 2027 (+14 months)+14 mo
- Fleet EGH (Tertiary)England and Wales, Storage with solar or windStage 1: Status changed from Awaiting Consents to Consents Approved
- Fleet EGH (Tertiary)England and Wales, Storage with solar or windStage removed (7.1 MW from 31 Oct 2026)
- Fleet EGH (Tertiary)England and Wales, Storage with solar or windCustomer changed from ENSO GREEN HOLDINGS LIMITED to Fleet Green Limited
- Fleet Solar PVEngland and Wales, SolarAdded to the registerNew
- Fleet EGH (Tertiary)England and Wales, Storage with solar or windSubstation name updated in the register (from Fleet GSP to Fleet 400kV Substation)
- Fleet (Tertiary)England and Wales, SolarSubstation name updated in the register (from Fleet 400kV to Fleet 400kV Substation)
- Fleet EGH (Tertiary)England and Wales, Storage with solar or windSubstation name updated in the register (from Fleet to Fleet GSP)
- Fleet TertiaryEngland and Wales, Thermal (gas, biomass, waste)Substation name updated in the register (from Fleet 400kV to Fleet 400kV Substation)
- Fleet TertiaryEngland and Wales, Thermal (gas, biomass, waste)Capacity changed from 57 MW to 47.5 MW
- Fleet TertiaryEngland and Wales, Thermal (gas, biomass, waste)Connection date moved from 1 May 2024 to 30 Nov 2025 (+19 months)+19 mo
- Fleet EGH (Tertiary)England and Wales, Storage with solar or windSubstation name updated in the register (from Fleet 400kV to Fleet)
- Fleet (Tertiary)England and Wales, SolarCapacity changed from 49.9 MW to 47.5 MW
- Fleet (Tertiary)England and Wales, SolarConnection date moved from 10 Jan 2025 to 31 Oct 2025 (+10 months)+10 mo
- Fleet EGH (Tertiary)England and Wales, Storage with solar or windRenamed from Fleet (Tertiary)
- Fleet (Tertiary)England and Wales, SolarConnection date moved from 1 Oct 2025 to 10 Jan 2025 (−9 months)−9 mo
- Fleet TertiaryEngland and Wales, Thermal (gas, biomass, waste)Connection date moved from 5 Jan 2024 to 1 May 2024 (+4 months)+4 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose