CSE23 LIMITED
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Fleet (Tertiary) | Fleet 400kV Substation | Solar | 47.5 | 30 Jul 2029 +33 mo | Gate 2 | Consents Approved |
Recent changes
- Fleet (Tertiary)England and Wales, SolarGiven a Gate 2 connection offerGate 2
- Fleet (Tertiary)England and Wales, SolarConnection date moved from 31 Oct 2026 to 30 Jul 2029 (+33 months)+33 mo
- Fleet (Tertiary)England and Wales, SolarStatus changed from Scoping to Consents Approved
- Fleet (Tertiary)England and Wales, SolarConnection date moved from 31 Oct 2025 to 31 Oct 2026 (+12 months)+12 mo
- Fleet (Tertiary)England and Wales, SolarSubstation name updated in the register (from Fleet 400kV to Fleet 400kV Substation)
- Fleet (Tertiary)England and Wales, SolarCapacity changed from 49.9 MW to 47.5 MW
- Fleet (Tertiary)England and Wales, SolarConnection date moved from 10 Jan 2025 to 31 Oct 2025 (+10 months)+10 mo
- Fleet (Tertiary)England and Wales, SolarConnection date moved from 1 Oct 2025 to 10 Jan 2025 (−9 months)−9 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?