Fleet Tertiary
- Connection date
- 7 Aug 2028 +32 months since 9 Dec
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Thermal
- Total capacity
- 47.5 MW
- Connected now
- 0 MW
- Still to connect
- 47.5 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-000429
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 10 Oct 2026 registerMarked as Gate 1
- 7 Aug 2026 registerConnection date moved from 30 Nov 2025 to 7 Aug 2028 (+32 months)
- 23 Dec 2022 registerSubstation name updated in the register (from Fleet 400kV to Fleet 400kV Substation)
- 30 Jun 2022 registerCapacity changed from 57 MW to 47.5 MW
- 30 Jun 2022 registerConnection date moved from 1 May 2024 to 30 Nov 2025 (+19 months)
- 26 Feb 2021 registerConnection date moved from 5 Jan 2024 to 1 May 2024 (+4 months)
Also at Fleet 400kV Substation
Substation view3 other projects, 200 MW still to connect at this substation in total. 47.5 MW is due to connect here before this project’s connection date of 7 Aug 2028.