Fleet (Tertiary)
- Connection date
- 30 Jul 2029 +33 months since 9 Dec
- Gate
- Gate 2
- Status
- Consents Approved
- Technology
- Solar
- Total capacity
- 47.5 MW
- Connected now
- 0 MW
- Still to connect
- 47.5 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001087
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 16 Oct 2026 registerGiven a Gate 2 connection offer
- 1 Oct 2026 registerConnection date moved from 31 Oct 2026 to 30 Jul 2029 (+33 months)
- 28 Feb 2025 registerStatus changed from Scoping to Consents Approved
- 31 Jan 2025 registerConnection date moved from 31 Oct 2025 to 31 Oct 2026 (+12 months)
- 23 Dec 2022 registerSubstation name updated in the register (from Fleet 400kV to Fleet 400kV Substation)
- 29 Oct 2021 registerCapacity changed from 49.9 MW to 47.5 MW
- 29 Oct 2021 registerConnection date moved from 10 Jan 2025 to 31 Oct 2025 (+10 months)
- 26 Feb 2021 registerConnection date moved from 1 Oct 2025 to 10 Jan 2025 (−9 months)
Also at Fleet 400kV Substation
Substation view3 other projects, 200 MW still to connect at this substation in total. 152 MW is due to connect here before this project’s connection date of 30 Jul 2029.