Fleet EGH (Tertiary)
- Connection date
- 13 Jan 2027
- Gate
- Not stated
- Status
- Consents Approved
- Technology
- Storage + Solar
- Total capacity
- 47.5 MW
- Connected now
- 0 MW
- Still to connect
- 47.5 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-000544
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 27 Aug 2024 registerStage 1: Capacity changed from 49.9 MW to 47.5 MW
- 27 Aug 2024 registerStage 1: Connection date moved from 31 Oct 2025 to 13 Jan 2027 (+14 months)
- 27 Aug 2024 registerStage 1: Status changed from Awaiting Consents to Consents Approved
- 27 Aug 2024 registerStage removed (7.1 MW from 31 Oct 2026)
- 30 Jul 2024 registerCustomer changed from ENSO GREEN HOLDINGS LIMITED to Fleet Green Limited
- 28 Jul 2023 registerSubstation name updated in the register (from Fleet GSP to Fleet 400kV Substation)
- 23 Dec 2022 registerSubstation name updated in the register (from Fleet to Fleet GSP)
- 28 Jan 2022 registerSubstation name updated in the register (from Fleet 400kV to Fleet)
- 29 Oct 2021 registerRenamed from Fleet (Tertiary)
Also at Fleet 400kV Substation
Substation view3 other projects, 200 MW still to connect at this substation in total.