VPI Power Limited
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Damhead Creek 2 | Kingsnorth 400kV Substation | Thermal (gas, biomass, waste) | 1,800 | 31 Oct 2030 +62 mo | Not stated | Consents Approved |
| Damhead Creek | Kingsnorth GSP | Thermal (gas, biomass, waste) | 0 | Connected | Not stated | Built |
| Rye House | Rye House GSP | Thermal (gas, biomass, waste) | 0 | Connected | Not stated | Built |
| Shoreham | Bolney 400kV Substation | Thermal (gas, biomass, waste) | 0 | Connected | Not stated | Built |
Recent changes
- Damhead Creek 2England and Wales, Thermal (gas, biomass, waste)Connection date moved from 31 Aug 2025 to 31 Oct 2030 (+62 months)+62 mo
- ShorehamEngland and Wales, Thermal (gas, biomass, waste)Connected MW moved between stages in the register (460 MW connected, unchanged)
- ShorehamEngland and Wales, Thermal (gas, biomass, waste)Stage removed (40 MW connected)
- ShorehamEngland and Wales, Thermal (gas, biomass, waste)Stage removed (−40 MW from 1 Oct 2026)
- ShorehamEngland and Wales, Thermal (gas, biomass, waste)Stage removed (40 MW from 31 Dec 2029)
- Damhead Creek 2England and Wales, Thermal (gas, biomass, waste)Technology changed from Gas (CCGT) to Gas (CCGT), Storage, Gas (OCGT)
- ShorehamEngland and Wales, Thermal (gas, biomass, waste)Connection point changed from Bolney GSP to Bolney 400kV Substation
- Damhead CreekEngland and Wales, Thermal (gas, biomass, waste)Substation name updated in the register (from Kingsnorth to Kingsnorth GSP)
- Rye HouseEngland and Wales, Thermal (gas, biomass, waste)Substation name updated in the register (from Rye House to Rye House GSP)
- Damhead Creek 2England and Wales, Thermal (gas, biomass, waste)Substation name updated in the register (from Kingsnorth 400kV to Kingsnorth 400kV Substation)
- Damhead Creek 2England and Wales, Thermal (gas, biomass, waste)Connection date moved from 31 Aug 2024 to 31 Aug 2025 (+12 months)+12 mo
- ShorehamEngland and Wales, Thermal (gas, biomass, waste)Substation name updated in the register (from Bolney to Bolney GSP)
- ShorehamEngland and Wales, Thermal (gas, biomass, waste)Stage 1: 40 MW now connectedConnected
- ShorehamEngland and Wales, Thermal (gas, biomass, waste)Stage 1: Status changed from Under Construction/Commissioning to Built
- Damhead Creek 2England and Wales, Thermal (gas, biomass, waste)Connection date moved from 30 Sep 2022 to 31 Aug 2024 (+23 months)+23 mo
- ShorehamEngland and Wales, Thermal (gas, biomass, waste)New stage added (40 MW from 1 Sep 2021)
- ShorehamEngland and Wales, Thermal (gas, biomass, waste)New stage added (−40 MW from 1 Oct 2026)
- ShorehamEngland and Wales, Thermal (gas, biomass, waste)New stage added (40 MW from 31 Dec 2029)
- Damhead CreekEngland and Wales, Thermal (gas, biomass, waste)Customer changed from DRAX GENERATION ENTERPRISE LIMITED to VPI POWER LIMITED
- Damhead Creek 2England and Wales, Thermal (gas, biomass, waste)Customer changed from DRAX GENERATION ENTERPRISE LIMITED to VPI POWER LIMITED
- Rye HouseEngland and Wales, Thermal (gas, biomass, waste)Customer changed from DRAX GENERATION ENTERPRISE LIMITED to VPI POWER LIMITED
- ShorehamEngland and Wales, Thermal (gas, biomass, waste)Customer changed from DRAX GENERATION ENTERPRISE LIMITED to VPI POWER LIMITED
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?