LAND AT LOCKS FARM

INTELLIGENT ALTERNATIVES LIMITED at BOTLEY WOOD GSP

SSEN Embedded Capacity Register, November 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Target energisation date
31 Aug 2026
Status
Accepted to connect
Planning consent
Granted 9 Jun 2023
Winchester, reference 21/01391/FUL · Source: REPD
Contract for Difference
Allocation Round 6
Customer
INTELLIGENT ALTERNATIVES LIMITED
Site name
LAND AT LOCKS FARM
Address
LAND AT LOCKS FARM, BOTLEY ROAD BISHOPS WALTHAM, SOUTHAMPTON, HAMPSHIRE, SO32 1DR
Grid reference
Easting 454655, northing 116565
Licence area
Southern England (SEPD)
Grid supply point
BOTLEY WOOD GSP
Bulk supply point
BOTLEY WOOD
Primary substation
Not stated
Connection voltage
33 kV
Technology group
Solar
Energy source 1
SOLAR, PHOTOVOLTAIC: 12 MW registered
Registered capacity
12 MW
Change to maximum export capacity
12 MW
Change to maximum import capacity
0.211 MW
Flexible connection
Not stated
In a connection queue
Not published by SSEN
Date accepted
4 Mar 2024
Date connected
Not stated
Distribution reinforcement reference
Not published by SSEN
Transmission reinforcement reference
Not published by SSEN
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
10 Feb 2026
Tracked since
April 2024 edition

Change history

Tracked since the April 2024 edition, across 32 editions.

Changes to the details QueueWatch tracks, newest first.

  • November 2025 edition
    Target energisation date stated as 31 Aug 2026 (not stated in the October 2025 edition)

Also at BOTLEY WOOD GSP

GSP view

16 other sites at this grid supply point in the November 2026 edition. In all, the sites here total 421 MW: 103 MW connected, 318 MW accepted to connect.

See all 16

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Planning consent

The planning decision or stage for this site, from DESNZ’s Renewable Energy Planning Database (REPD), October 2026 edition, with the planning authority and its reference. QueueWatch matched the site to that record. The register’s status can lag behind planning decisions, so the two may differ.

How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.

Contract for Difference

The Contracts for Difference allocation round for this site, from DESNZ’s Renewable Energy Planning Database (REPD), October 2026 edition. QueueWatch matched the site to that record.

How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.