Distribution / SSEN / Grid supply point

BOTLEY WOOD GSP

Grid supply point in Southern England (SEPD)

SSEN Embedded Capacity Register, September 2026 edition

17sites of 1 MW and over
421 MWcapacity
103 MWconnected (8 sites)
318 MWaccepted to connect (9 sites)

Capacity by technology

TechnologySitesCapacityConnectedAccepted to connect
Storage4215 MW50 MW165 MW
Solar10135 MW32 MW103 MW
Other or not stated269.4 MW19 MW50.4 MW
Bioenergy and waste11.2 MW1.2 MW–

Storage capacity in MWh: not published by SSEN.

Each site is grouped by its first energy source, as the register names it.

How busy is each primary substation?

Each primary substation at this grid supply point in the September 2026 edition, under the bulk supply point its register gives. Select a row to see its sites.

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Primary substationBulk supply pointSitesConnectedAccepted to connect
BOTLEY WOOD3–115 MW
BOTLEY WOOD119 MW–
BOTLEY WOOD1–3.8 MW
BOTLEY WOOD350 MW112 MW
NETLEY COMMON37.3 MW10 MW
NETLEY COMMON111.4 MW–
NETLEY COMMON19.5 MW–
NETLEY COMMON11.2 MW–
NETLEY COMMON24.4 MW27 MW
Not stated1–50.4 MW

Not found in SSEN's September 2026 edition

6 sites last found at this grid supply point were not found in this edition by their MPAN, grid reference or name and postcode. QueueWatch keeps their pages for six months and does not say whether they have left the register.

What changed recently

Changes to the sites here found in both of two consecutive monthly editions, the latest first.

August 2026 edition to September 2026 edition: 17 sites matched. Every August site and every September site at this grid supply point had a match in the other edition.

  • NETLEY PVNovember 2023 editionCapacity changed from 4.625 MW to 4.394 MW
  • NETLEY PVNovember 2023 editionCustomer changed from ETHICAL POWER to EPG NETLEY SOLAR NORTH LIMITED
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs' published connection registers. It doesn't tell you what to do about it. That's what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

How power reaches a site

A grid supply point (GSP) is where the national grid hands power to the local network. A bulk supply point (BSP) steps it down to a lower voltage for an area. A primary substation steps it down again for the streets and sites nearby. Most small and medium sites connect at a primary. Not every network has all three levels.