HEYSHAM GSP
Grid supply point in North West England (ENWL)
ENWL Embedded Capacity Register 2 – 1MW and above, September 2026 edition
The register spells this grid supply point more than one way: “HEYSHAM GSP” (25 sites) and “HEYSHAM” (5 sites).
Capacity by technology
| Technology | Sites | Capacity | Connected | Accepted to connect |
|---|---|---|---|---|
| Storage | 8 | 780 MW | – | 780 MW |
| Wind | 5 | 266 MW | 266 MW | – |
| Gas and other fossil | 3 | 58.1 MW | 7.6 MW | 50.5 MW |
| Solar | 7 | 52 MW | 11.5 MW | 40.5 MW |
| Other or not stated | 1 | 35.8 MW | – | 35.8 MW |
| Bioenergy and waste | 6 | 6.5 MW | 5.4 MW | 1.1 MW |
Storage capacity in MWh: not published by ENWL.
Each site is grouped by its first energy source, as the register names it.
How busy is each primary substation?
Each primary substation at this grid supply point in the September 2026 edition, under the bulk supply point its register gives. Select a row to see its sites.
Site, company and substation names are shown as they appear in the registers, including capitalisation.
| Primary substation | Bulk supply point | Sites | Connected | Accepted to connect | ||||||||||||||||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| ROYTON | 1 | – | 240 MW | |||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 240 MW: 240 MW accepted to connect
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||
| LANCASTER | 5 | 7.5 MW | 20.5 MW | |||||||||||||||||||||||||||||||||||||||||||||||||||
5 sites, 28 MW: 7.5 MW connected, 20.5 MW accepted to connect
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||
| LANCASTER | 4 | 7 MW | 1.1 MW | |||||||||||||||||||||||||||||||||||||||||||||||||||
4 sites, 8.1 MW: 7 MW connected, 1.1 MW accepted to connect
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||
| LANCASTER | 3 | 7.3 MW | – | |||||||||||||||||||||||||||||||||||||||||||||||||||
3 sites, 7.3 MW: 7.3 MW connected
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||
| LANCASTER | 2 | 4 MW | – | |||||||||||||||||||||||||||||||||||||||||||||||||||
2 sites, 4 MW: 4 MW connected
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||
| LANCASTER | 1 | 1.1 MW | – | |||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 1.1 MW: 1.1 MW connected
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||
| LANCASTER | 3 | 16 MW | 45 MW | |||||||||||||||||||||||||||||||||||||||||||||||||||
3 sites, 61 MW: 16 MW connected, 45 MW accepted to connect
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||
| MIDDLETON | 1 | – | 99.9 MW | |||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 99.9 MW: 99.9 MW accepted to connect
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||
| TRIMPELL | 1 | 7.5 MW | – | |||||||||||||||||||||||||||||||||||||||||||||||||||
1 site, 7.5 MW: 7.5 MW connected
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Not stated | 9 | 240 MW | 501 MW | |||||||||||||||||||||||||||||||||||||||||||||||||||
9 sites, 741 MW: 240 MW connected, 501 MW accepted to connect
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||
What changed recently
Changes to the sites here found in both of two consecutive monthly editions, the latest first.
May 2026 edition to September 2026 edition: 30 sites matched. Every May site and every September site at this grid supply point had a match in the other edition.
No change to the status, capacity, technology or customer of the sites here in the editions of ENWL's register QueueWatch holds.
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs' published connection registers. It doesn't tell you what to do about it. That's what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
How power reaches a site
A grid supply point (GSP) is where the national grid hands power to the local network. A bulk supply point (BSP) steps it down to a lower voltage for an area. A primary substation steps it down again for the streets and sites nearby. Most small and medium sites connect at a primary. Not every network has all three levels.