QAIR RENEWABLES UK LIMITED
Customer named in the TEC register
Projects
Recent changes
- Hill FarmEngland and Wales, StorageConnection date moved from 30 Oct 2035 to 30 Oct 2037 (+24 months)+24 mo
- Wacton Road FarmEngland and Wales, StorageConnection date moved from 30 Oct 2034 to 31 Oct 2034 (1 day later)
- Church Road FarmEngland and Wales, StorageMarked as Gate 1
- Manor FarmEngland and Wales, StorageConnection date moved from 30 Oct 2038 to 31 Oct 2034 (−48 months)−48 mo
- Hill FarmEngland and Wales, StorageConnection date moved from 31 Oct 2037 to 30 Oct 2035 (−24 months)−24 mo
- Manor FarmEngland and Wales, StorageConnection date moved from 31 Oct 2034 to 30 Oct 2038 (+48 months)+48 mo
- Red Moss FarmSouth Scotland, StorageConnection date moved from 30 Oct 2030 to 30 May 2031 (+7 months)+7 mo
- Wacton Road FarmEngland and Wales, StorageConnection date moved from 31 Oct 2034 to 30 Oct 2034 (1 day earlier)
- Hill FarmEngland and Wales, StorageMarked as Gate 1
- Strawberry FarmEngland and Wales, StorageMarked as Gate 1
- Strawberry FarmEngland and Wales, StorageConnection point changed from Walpole GSP (EPN) to North Anglia Connection Node D 132kV Substation
- Wacton Road FarmEngland and Wales, StorageMarked as Gate 1
- Wymondham Road FarmEngland and Wales, StorageConnection point changed from Norwich GSP to North Anglia Connection Node A 132kV Substation
- Wymondham Road FarmEngland and Wales, StorageMarked as Gate 1
- Red Moss FarmSouth Scotland, StorageMarked as Gate 1
- Dalchork FarmNorth Scotland, StorageMarked as Gate 1
- Brae House FarmNorth Scotland, StorageConnection point changed from Dounreay to DOUNREAY 2 275 kV SUBSTATION
- Brae House FarmNorth Scotland, StorageMarked as Gate 1
- Craig Moss FarmSouth Scotland, StorageMarked as Gate 1
- Church Road FarmEngland and Wales, StorageConnection point changed from Burwell GSP to South Anglia Connection Node D 132kV Substation
- South Powrie FarmNorth Scotland, StorageMarked as Gate 1
- Manor FarmEngland and Wales, StorageMarked as Gate 1
- Fairmead and Yewtree FarmEngland and Wales, StorageMarked as Gate 1
- Penrhiwdarren FarmEngland and Wales, StorageMarked as Gate 1
- Whiteleigh FarmEngland and Wales, Storage with solar or windMarked as Gate 1
- Church Road FarmEngland and Wales, StorageAdded to the registerNew
- Strawberry FarmEngland and Wales, StorageAdded to the registerNew
- Craig Moss FarmSouth Scotland, StorageTechnology changed from Storage, Solar to Storage
- Wacton Road FarmEngland and Wales, StorageAdded to the registerNew
- Wymondham Road FarmEngland and Wales, StorageAdded to the registerNew
- Manor FarmEngland and Wales, StorageConnection point changed from South Anglia Connection Node E 400kV Substation to East Anglia Connection Node E 400kV Substation
- Red Moss FarmSouth Scotland, StorageConnection point changed from Red Moss GSP to Red Moss Farm 132kV Substation
- Brae House FarmNorth Scotland, StorageCustomer changed from Greenswitch Capital Limited to QAIR RENEWABLES UK LIMITED
- Craig Moss FarmSouth Scotland, StorageCustomer changed from Greenswitch Capital Limited to QAIR RENEWABLES UK LIMITED
- Dalchork FarmNorth Scotland, StorageCustomer changed from Greenswitch Capital Limited to QAIR RENEWABLES UK LIMITED
- Fairmead and Yewtree FarmEngland and Wales, StorageCustomer changed from Greenswitch Capital Limited to QAIR RENEWABLES UK LIMITED
- Hill FarmEngland and Wales, StorageCustomer changed from Greenswitch Capital Limited to QAIR RENEWABLES UK LIMITED
- Manor FarmEngland and Wales, StorageCustomer changed from Greenswitch Capital Limited to QAIR RENEWABLES UK LIMITED
- Manor FarmEngland and Wales, StorageConnection point changed from Sizewell 400kV Substation to South Anglia Connection Node E 400kV Substation
- Manor FarmEngland and Wales, StorageConnection date moved from 30 Oct 2034 to 31 Oct 2034 (1 day later)
- Penrhiwdarren FarmEngland and Wales, StorageCustomer changed from Greenswitch Capital Limited to QAIR RENEWABLES UK LIMITED
- Red Moss FarmSouth Scotland, StorageCustomer changed from Greenswitch Capital Limited to QAIR RENEWABLES UK LIMITED
- Roger Hill FarmSouth Scotland, Storage with solar or windCustomer changed from Greenswitch Capital Limited to QAIR RENEWABLES UK LIMITED
- South Powrie FarmNorth Scotland, StorageCustomer changed from Greenswitch Capital Limited to QAIR RENEWABLES UK LIMITED
- Whiteleigh FarmEngland and Wales, Storage with solar or windCustomer changed from Greenswitch Capital Limited to QAIR RENEWABLES UK LIMITED
- Manor FarmEngland and Wales, StorageAdded to the registerNew
- Fairmead and Yewtree FarmEngland and Wales, StorageConnection date moved from 31 Oct 2031 to 31 Oct 2037 (+72 months)+72 mo
- Dalchork FarmNorth Scotland, StorageSubstation name updated in the register (from Dalchork Substation 132 kV to Dalchork 132kV Substation)
- Brae House FarmNorth Scotland, StorageAdded to the registerNew
- Fairmead and Yewtree FarmEngland and Wales, StorageConnection point changed from Sellindge 400kV Substation to East Kent connection node A 400kV Substation
- South Powrie FarmNorth Scotland, StorageAdded to the registerNew
- Fairmead and Yewtree FarmEngland and Wales, StorageAdded to the registerNew
- Hill FarmEngland and Wales, StorageAdded to the registerNew
- Dalchork FarmNorth Scotland, StorageAdded to the registerNew
- Red Moss FarmSouth Scotland, StorageAdded to the registerNew
- Penrhiwdarren FarmEngland and Wales, StorageAdded to the registerNew
- Roger Hill FarmSouth Scotland, Storage with solar or windAdded to the registerNew
- Craig Moss FarmSouth Scotland, StorageAdded to the registerNew
- Whiteleigh FarmEngland and Wales, Storage with solar or windAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?