North Anglia Connection Node D 132kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Strawberry Farm | QAIR RENEWABLES UK LIMITED | Storage | 278 | 31 Oct 2034 | Gate 1 | Scoping |
| Walsoken Battery | Walsoken Limited | Storage | 200 | 31 Oct 2034 | Not stated | Scoping |
Recent changes
- Strawberry FarmEngland and Wales, StorageMarked as Gate 1
- Strawberry FarmEngland and Wales, StorageConnection point changed from Walpole GSP (EPN) to North Anglia Connection Node D 132kV Substation
- Strawberry FarmEngland and Wales, StorageAdded to the registerNew
- Walsoken BatteryEngland and Wales, StorageConnection date moved from 30 Oct 2033 to 31 Oct 2034 (+12 months)+12 mo
- Walsoken BatteryEngland and Wales, StorageConnection point changed from Walpole 132kV Substation to North Anglia Connection Node D 132kV Substation
- Walsoken BatteryEngland and Wales, StorageAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?